Author Topic: SR 641, What's taking so long for construction to begin?  (Read 3657 times)

US 41

  • *
  • Offline Offline

  • Posts: 1885
  • Age: 27
  • Location: Terre Haute, IN
  • Last Login: February 04, 2024, 09:59:20 PM
SR 641, What's taking so long for construction to begin?
« on: April 24, 2013, 09:19:21 AM »

Last year INDOT said they were going to start construction on SR 641. The consruction was supposed to start in the fall on the roundabouts at the future SR 641 / SR 46 / Riley Road Interchange. It is now late April and there has been no construction at all. Trees are cleared, but that's it. They were done with that part a long time ago. They haven't even started tearing the houses down yet. No one lives in them now obviously, but what I don't get is what is taking so long? Does anyone on here have any answers to this question. If so please let me know. Thanks.
Logged
Visited States and Provinces:
USA (48)= All of Lower 48
Canada (5)= NB, NS, ON, PEI, QC
Mexico (9)= BCN, BCS, CHIH, COAH, DGO, NL, SON, SIN, TAM

silverback1065

  • *
  • Offline Offline

  • Posts: 4131
  • Age: 34
  • Last Login: March 18, 2024, 08:22:25 AM
Re: SR 641, What's taking so long for construction to begin?
« Reply #1 on: April 24, 2013, 10:02:17 AM »

I thought I heard somewhere that SR 641 won't be done for a very long time, I don't think it's a high priority or maybe they don't have the funding yet
Logged

mukade

  • *
  • Offline Offline

  • Posts: 1303
  • Location: Indiana
  • Last Login: January 10, 2024, 08:05:39 AM
    • Highway Explorer
Re: SR 641, What's taking so long for construction to begin?
« Reply #2 on: April 24, 2013, 07:25:49 PM »

A phase of State Road 641 (S.R. 641) project was awarded to Walsh Construction Co. of Crown Point, IN for $25,298,936 in January 2012.  The Major Moves contract is for new road and bridge construction on S.R. 641 from a quarter mile north of Feree Road to three and one half miles north of Riley Road.

Construction was expected to begin April 1 and be completed by the fall of 2013.  The entire bypass, connecting US 41 on the south to I-70 on the north should be open to traffic by the end of the construction season in 2014.

The next phase of the project is scheduled to be let on 12/11/2013 and has been scheduled for that date for at least a couple of months.

I-70 Westbound over SR 641
I-70 Eastbound over SR 641
Local service road over Tributary to Lilttle Honey Creek
Moyer Road over Little Honey Creek
SR641 from just south of Moyer Rd. to Margaret Ave.
SR 641 over Tributary to Little Honey Creek
Moyer Road over SR 641

All of this is on the INDOT web site.
Logged

tdindy88

  • *
  • Offline Offline

  • Posts: 1887
  • Last Login: Today at 06:31:21 AM
Re: SR 641, What's taking so long for construction to begin?
« Reply #3 on: April 24, 2013, 08:25:45 PM »

I'm curious, is there a contract number for this one. I've been a little curious about the signage along this stretch of SR 641, such as the interchange with I-70. For instance, will Evansville be signed at that exit and will SR 46 be mentioned (I thought there had been talk about the truncation of the the highway to its new interchange with 641, thought that may have been put on hold.)
Logged

J N Winkler

  • *
  • *
  • Offline Offline

  • Posts: 8772
  • Location: Wichita, Kansas
  • Last Login: Today at 02:48:46 AM
Re: SR 641, What's taking so long for construction to begin?
« Reply #4 on: April 27, 2013, 08:49:43 PM »

Regarding contract numbers:  the bits of SR 641 that are currently active are Phases III (contract number 30089) and Phase IV (contract number 30091).  Netservices has the complete plans assembly for 30089 but nothing for 30091, so I think it is probably the one that is still to be advertised.  30089 (for which I have extracted the sign panel detail sheets) just deals with SR 46 and Riley Road.
Logged
"It is necessary to spend a hundred lire now to save a thousand lire later."--Piero Puricelli, explaining the need for a first-class road system to Benito Mussolini

 


Opinions expressed here on belong solely to the poster and do not represent or reflect the opinions or beliefs of AARoads, its creators and/or associates.