News:

Thanks to everyone for the feedback on what errors you encountered from the forum database changes made in Fall 2023. Let us know if you discover anymore.

Main Menu

Timeline of road projects

Started by Albert, July 28, 2022, 02:22:39 PM

Previous topic - Next topic

Albert

OR 42 project Adams to Finley: 2021 - Leveled parts of highway bypass (built 1990s) that are 6 ft. higher than level and restriped

Replaced some Curb ramps

East of Coquille: Highway ground, repaved, and restriped to include a Center Turn Lane

2022 - Replaced some more curb ramps and built a new pedestrian island

Already leveled, older bypass parts ground and repaved, then new overlay put on top of that and existing pavement and striped

Project completion - Sep. 2022



Opinions expressed here on belong solely to the poster and do not represent or reflect the opinions or beliefs of AARoads, its creators and/or associates.