AARoads Forum

National Boards => Bridges => Topic started by: seicer on July 25, 2013, 02:56:07 PM

Title: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: seicer on July 25, 2013, 02:56:07 PM
Milton-Madison Bridge's Main Span Demolished (http://bridgestunnels.com/2013/07/25/milton-madison-bridges-main-span-demolished/)

The Milton-Madison Bridge (http://bridgestunnels.com/bridges/ohio-river/milton-madison-bridge-us-421) connects Milton, Kentucky to Madison, Indiana and carries US 421 over the Ohio River. The historic two-lane Cantilever was rehabilitated in 1997, but was deemed to be in poor structural condition by 2006. Rehabilitation options were considered for the crossing, which would have extended the life of the bridge another ten years before needing additional work. Ultimately, the Kentucky Transportation Cabinet (KYTC) and the Indiana Department of Transportation (INDOT) agreed to replace the aging span in the summer of 2008.

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-us-421%2F20130723-_dsc3781.jpg&hash=33146b9dcb28ef6173acdb65070ec4945f1e3534) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-us-421/20130723-_dsc3781.jpg)

A construction contract was awarded to Walsh Construction for $103.9 million in September 2010 and ground was broken on November 30. Construction began two months later which involved strengthening the existing piers and constructing temporary approach spans to allow for the replacement of the original approaches. Construction on a 600-f00t truss began along the banks of the river, and was floated upstream and lifted into place onto temporary piers adjacent to the existing bridge. A second truss, 727-foot long, was then constructed and lifted onto temporary piers. The remaining components for the bridge were constructed on top of the temporary piers using conventional cranes.

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-us-421%2F20130723-_dsc3816.jpg&hash=f6dfd3cd1e7a319ffcbd47452d3e9f7bf2879f41) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-us-421/20130723-_dsc3816.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-us-421%2F20130723-_dsc3914.jpg&hash=275df691e3789d321373c4bd240d2c2fd1eaa857) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-us-421/20130723-_dsc3914.jpg)

Traffic was rerouted onto the new bridge via temporary ramps in April 2012, and on June 3, 2013, vehicles were switched to the new trusses, allowing for the removal of the bridge decks on the old spans. On July 23, a 700-foot span over the main navigational channel was demolished with small explosive charges from Advanced Explosives Demolition.

The use of temporary piers and ramps will lead to a total bridge closure time of less than ten days, less than an earlier projected closure date of one year. The new bridge, which will include a pedestrian sidewalk and bike lanes, is expected to open by September 2013.

Below: The demolition of the main span of the Milton-Madison Bridge on July 23.

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3618.jpg&hash=11406910b110dcae629d136699418da8dc3e2bfc) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3618.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3619.jpg&hash=61d0074a630965a35779285e84807d38c47a032e) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3619.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3620.jpg&hash=2b1a676ce2d5417c98eeb1664585c91473a648dd) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3620.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3621.jpg&hash=901ae4b98f929ffce77a4f72a1e4a7bb0e5cc372) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3621.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3622.jpg&hash=cbc6530a68fbc74bb011d1c5763f92e83de92d44) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3622.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3623.jpg&hash=ea3299a68013f7073b8fceeb9df658ed29aa6e9c) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3623.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3624.jpg&hash=cf7ffc4ec916e0fb3fed7a73e456b3ad0c5a2297) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3624.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3625.jpg&hash=6783008a96f617f0ff896a795521b8e8ae91078f) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3625.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3626.jpg&hash=2206b73473398d08bf86b78b0d12ca9b4540a464) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3626.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3627.jpg&hash=2feb27543b7c2520c556c4f0e88b24a0cedd3062) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3627.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3628.jpg&hash=7ea549640faec5dd6fdbb6810e05f31c5e09d504) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3628.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3629.jpg&hash=6bf5e4d9fcc0fd5e82a3f9af5167ee93a8e63e08) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3629.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3630.jpg&hash=e47d7d70aed5816d60a6e0a4816a012f4c50201c) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3630.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3631.jpg&hash=eabf1d61dc914d8976d70be00932838e33f8071a) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3631.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3632.jpg&hash=01558bfcf8710b1a935b28611c5e9a7ccc405786) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3632.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3633.jpg&hash=925fd5dd366a9e5b2a38826778d3e33ceda9aad8) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3633.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3634.jpg&hash=1b6ca396fa6d266449c5c4016b5fd00f7a5ef5da) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3634.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3635.jpg&hash=1590b64ea63c7dfce9a4a3684806b6b23a1efff4) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3635.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3636.jpg&hash=b04b134c3dca21e5cc23ebf3c7cb6f9794519578) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3636.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3638.jpg&hash=1c2ccfaa6d814a485b859a21109c8bad45633749) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3638.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3764.jpg&hash=f35d56d9773f7a116850af6f3c64960828e058bf) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3764.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3828.jpg&hash=479b6087ced18c7257675b6b4a255b8bf2950459) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3828.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3904.jpg&hash=04fd32ece51613f28effb635a5af7de20595053e) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3904.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3938.jpg&hash=48a801ee7bf13ddd2a0b85f925dbe470898651a2) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3938.jpg)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fbridgestunnels.com%2Fwp-content%2Fgallery%2Fmilton-madison-bridge-construction%2F20130723-_dsc3941.jpg&hash=363a581f604485d7be38bb5ebd1fa46c8d5eff27) (http://bridgestunnels.com/wp-content/gallery/milton-madison-bridge-construction/20130723-_dsc3941.jpg)

More on the Milton-Madison Bridge » (http://bridgestunnels.com/bridges/ohio-river/milton-madison-bridge-us-421)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: agentsteel53 on July 25, 2013, 03:46:48 PM
looks like the demolition was not 100% successful?  or was the bridge intended to be hanging on to its pier still waiting for one final blast to sever it?
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: AsphaltPlanet on July 26, 2013, 07:47:35 PM
Neat photos.  I wonder if they deliberately left the bridge hanging in order to salvage the steel.  There is probably quite a bit of value there.  This would also avoid the environmental consequences as using the river bottom as a dump.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: theline on July 26, 2013, 08:58:59 PM
Thanks for those photos, Sherman. Terrific pictures, as usual.  :clap:

There is an interesting YouTube of the demolition, with a link posted in the Ohio Valley section, see here: https://www.aaroads.com/forum/index.php?topic=3891.msg234654#msg234654 (https://www.aaroads.com/forum/index.php?topic=3891.msg234654#msg234654)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on July 26, 2013, 09:39:20 PM
Quote from: AsphaltPlanet on July 26, 2013, 07:47:35 PM
Neat photos.  I wonder if they deliberately left the bridge hanging in order to salvage the steel.  There is probably quite a bit of value there.  This would also avoid the environmental consequences as using the river bottom as a dump.

The hang has to be un-intended. There is no intention of leaving any of the structure in the river as this is an active transportation corridor and they were only allowed 24 hours closure. 

The construction company has taken the debris to the Kentucky side for scrapping.

Also, there are two or three more demolitions over the next few weeks planned for the remaining spans.

Finally, not emphasized in the thread above, is the plan to slide the entire new span onto the alignment being cleared by the demolition.

There is quite a bit on the Ohio Valley thread for the US-421 bridge posted above.

see the official site; http://www.miltonmadisonbridge.com/news-center/ (http://www.miltonmadisonbridge.com/news-center/)

Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on July 27, 2013, 04:40:41 AM
Quote from: andy on July 26, 2013, 09:39:20 PM
Quote from: AsphaltPlanet on July 26, 2013, 07:47:35 PM
Neat photos.  I wonder if they deliberately left the bridge hanging in order to salvage the steel.  There is probably quite a bit of value there.  This would also avoid the environmental consequences as using the river bottom as a dump.

The hang has to be un-intended. There is no intention of leaving any of the structure in the river as this is an active transportation corridor and they were only allowed 24 hours closure. 

The construction company has taken the debris to the Kentucky side for scrapping.

Also, there are two or three more demolitions over the next few weeks planned for the remaining spans.

Finally, not emphasized in the thread above, is the plan to slide the entire new span onto the alignment being cleared by the demolition.

There is quite a bit on the Ohio Valley thread for the US-421 bridge posted above.

see the official site; http://www.miltonmadisonbridge.com/news-center/ (http://www.miltonmadisonbridge.com/news-center/)

I would bet that little piece hanging on was severed as they brought the adjoining part of the span on board whatever was used to haul the scrap away. Otherwise, that section could very well float downstream as they worked to remove the bridge from the water (I'm thinking that in order to maximize the available space on the barges and minimize the amount of trips, they cut it into more manageable "bite size" pieces).
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on July 27, 2013, 01:31:51 PM
Quote from: JMoses24 on July 27, 2013, 04:40:41 AM

I would bet that little piece hanging on was severed as they brought the adjoining part of the span on board whatever was used to haul the scrap away. Otherwise, that section could very well float downstream as they worked to remove the bridge from the water (I'm thinking that in order to maximize the available space on the barges and minimize the amount of trips, they cut it into more manageable "bite size" pieces).

I don't think there was any danger of floating.  They stripped the deck bare and the river isn't that deep or fast.

You can see the "bite size" removal on the time lapse video at; http://www.miltonmadisonbridge.com/gallery/live-web-cam/ (http://www.miltonmadisonbridge.com/gallery/live-web-cam/).  When you select July 23, it will set you to noon.  Backing up to 9:00 am, the span is still standing and 9:15, its in the river.  They didn't remove obvious parts until after lunch, but there were several "bites" removed as the day wore on.

Interestingly, they started removal on the Indiana side which was opposite the "hung" part but with 15 minute snaps, I don't know what else was done.

I'm not going to speculate on what they are doing, but it is important to remember these peers are to be re-used after the truss-slide, so they're not going to risk any damage to them.


Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on July 27, 2013, 11:54:53 PM
Quote from: andy on July 27, 2013, 01:31:51 PM
Quote from: JMoses24 on July 27, 2013, 04:40:41 AM

I would bet that little piece hanging on was severed as they brought the adjoining part of the span on board whatever was used to haul the scrap away. Otherwise, that section could very well float downstream as they worked to remove the bridge from the water (I'm thinking that in order to maximize the available space on the barges and minimize the amount of trips, they cut it into more manageable "bite size" pieces).

I don't think there was any danger of floating.  They stripped the deck bare and the river isn't that deep or fast.

You can see the "bite size" removal on the time lapse video at; http://www.miltonmadisonbridge.com/gallery/live-web-cam/ (http://www.miltonmadisonbridge.com/gallery/live-web-cam/).  When you select July 23, it will set you to noon.  Backing up to 9:00 am, the span is still standing and 9:15, its in the river.  They didn't remove obvious parts until after lunch, but there were several "bites" removed as the day wore on.

Interestingly, they started removal on the Indiana side which was opposite the "hung" part but with 15 minute snaps, I don't know what else was done.

I'm not going to speculate on what they are doing, but it is important to remember these peers are to be re-used after the truss-slide, so they're not going to risk any damage to them.

Right, they're strengthening the piers for re-use. However, the river doesn't necessarily need to be fast to send a small piece of steel downstream. I'm interested in how they configured the explosives, because you would think you want a clean break in the steel, unless the concern was that the explosives would have to be placed too close to the pier.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on July 30, 2013, 07:04:00 PM
Next demolition announced; http://www.miltonmadisonbridge.com/news-center/ (http://www.miltonmadisonbridge.com/news-center/)
PDF announcement with picture at http://www.miltonmadisonbridge.com/wp-content/uploads/2013/07/MMBP-2nd-Span-Blast-release2.pdf (http://www.miltonmadisonbridge.com/wp-content/uploads/2013/07/MMBP-2nd-Span-Blast-release2.pdf)

QuoteLouisville, Ky. (July 30, 2013) — A second section of the old US 421 Milton-Madison Bridge is scheduled to be demolished on Thursday, August 1, weather permitting. The 550-foot long section nearest the Milton, Ky., shore will be brought down using controlled explosives by Advanced Explosives Demolition Inc., the company that demolished another section of the bridge last week.
The demolition will require the closure of the new bridge starting at approximately 9:00 a.m. on August 1. Other roads within the designated 1,000-foot safety perimeter will also be closed.

I was able to get over to Madison Sunday and they were still picking small pieces out of the river.

Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on August 02, 2013, 12:13:28 AM
Second of three blasts was set off Thursday.

http://www.insideindianabusiness.com/newsitem.asp?id=60662&ts=true (http://www.insideindianabusiness.com/newsitem.asp?id=60662&ts=true)

This was a smaller blast.  It sounds like the remaining blast is expected next week.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on August 12, 2013, 11:33:14 AM
Oops...

http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=963&ArticleID=78254 (http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=963&ArticleID=78254)

I guess this is one of the hazards of a staged demolition (follow the link for a good picture);

QuoteContractors are bracing a portion of the old Madison-Milton Bridge that has shown significant bowing since the last bridge span demolition.

While reinforcement work is occurring overhead today, the secondary river channel - primarily used by recreational boaters - will be temporarily closed to river traffic.

The main navigational channel will remain open, and the new bridge also will remain open.

The southernmost section of the old bridge has been bowing since last week's demolition of a 550-foot span closest to Milton, a spokesman for Walsh Construction said.

When the loads were removed from the bridge, steel members at the top of the truss were compressed, causing them to bow, a press release said.

Engineers for Walsh Construction have assessed the old bridge and found it to be stable under current conditions.

Crews have demolished two spans of the old bridge using controlled explosives. Two demolitions remain but neither have been scheduled.

While large sections between the piers are being removed with explosives, sections of the truss directly over the piers will be removed manually using cranes to protect the piers which are being rehabilitated and reused.


update;
The current construction news (as of 8/12/2013) has more on that last paragraph.

http://www.miltonmadisonbridge.com/news-center/ (http://www.miltonmadisonbridge.com/news-center/)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on August 30, 2013, 11:55:41 PM
After what appears to have been a longer than expected delay, the next stage of the demolition has been set.

http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=961&ArticleID=78665&TM=84128.2 (http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=961&ArticleID=78665&TM=84128.2)

QuoteCrews remove portions of the old Madison-Milton Bridge on Thursday. Parts of the truss directly on top of the piers must be removed before each of the two remaining span blasts take place. The 400-foot section closest to Madison will be exploded at 9 a.m. Thursday. Residents inside the 1,000-foot blast zone should stay indoors starting at 8:45 a.m. until the blast is completed. The Madison Courier will post a map of the blast zone at www.madisoncourier.com.

I wonder if/how the partial demolition over the piers relates to the previously reported buckling on the south end.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 05, 2013, 02:33:28 PM
Another stage of the demolition this morning, some of the pictures;
from http://www.miltonmadisonbridge.com/gallery/live-web-cam/ (http://www.miltonmadisonbridge.com/gallery/live-web-cam/)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fwww.miltonmadisonbridge.com%2Fwp-content%2Fuploads%2Fgallery%2Fseptember-2013%2Fmadison-blast-3-ws-1.jpg&hash=05179de386506fdc5873e321783bfa9c386bd586)

Does the new truss look warped in this photo?
(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fwww.miltonmadisonbridge.com%2Fwp-content%2Fuploads%2Fgallery%2Fseptember-2013%2Fmadison-blast-3-gopro-2.jpg&hash=de170a24d8f3898507602a0b3d20ccbdce21ab13)

A nice photo of the truss linkages.  Easy to see the freely rotating pin joint instead of a riveted/bolted plate.

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fwww.miltonmadisonbridge.com%2Fwp-content%2Fuploads%2Fgallery%2Faugust-2013%2Ftruss-demo2.jpg&hash=05985ba8633d30fc00b8457809bf42d3ca07f1f4)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: agentsteel53 on September 05, 2013, 02:40:25 PM
Quote from: andy on September 05, 2013, 02:33:28 PM
Does the new truss look warped in this photo?

it does.  what's the explanation? 
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: seicer on September 05, 2013, 03:20:57 PM
Could be distortion in the lens. Just like a camera lens, some distortion is expected - but unlike a photographer's lens that can (usually) be corrected with software, video is much more difficult.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: DeaconG on September 05, 2013, 09:17:17 PM
Quote from: Sherman Cahal on September 05, 2013, 03:20:57 PM
Could be distortion in the lens. Just like a camera lens, some distortion is expected - but unlike a photographer's lens that can (usually) be corrected with software, video is much more difficult.

Looks like an ultra-wide angle, that would do it if the lens was at it's closest setting.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: seicer on September 05, 2013, 09:23:33 PM
Some lenses - especially cheap manufacturers or the low-end lenses of popular brands, will have complex signatures. I can't find anything about damage to the new span, though.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 06, 2013, 12:42:29 AM
I should have posted another photo. Later pictures looked better. I wonder if there might be a pressure wave distorting the air.

video at http://www.insideindianabusiness.com/newsitem.asp?id=61219&ts=true (http://www.insideindianabusiness.com/newsitem.asp?id=61219&ts=true)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: Duke87 on September 07, 2013, 10:36:53 PM
Quote from: andy on September 06, 2013, 12:42:29 AM
I should have posted another photo. Later pictures looked better. I wonder if there might be a pressure wave distorting the air.

Yeah, I was going to guess that heat from the explosions was distorting the image (think distant road surface looking blurry or reflecting the sky on a hot summer day).
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 11, 2013, 02:40:14 PM
Fourth and final demolition for next Tuesday (9/17)

https://twitter.com/mmbridgeproject (https://twitter.com/mmbridgeproject)
QuoteExplosive demolition of the remaining 600ft section of the old bridge is TENTATIVELY scheduled for Sept 17 at about 9am

And there's no way I can be there.  :-(
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: seicer on September 12, 2013, 10:08:06 AM
I might try.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on September 13, 2013, 03:53:42 AM
Quote from: Sherman Cahal on September 12, 2013, 10:08:06 AM
I might try.

It would be something to see for sure. One of the last pieces of the old, making way for the new in a sense (considering they are reusing the piers).
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 15, 2013, 01:17:52 AM
Update schedule;

https://twitter.com/mmbridgeproject (https://twitter.com/mmbridgeproject)
QuoteThe last span blast is now tentatively scheduled for Thursday, Sept 19 at about 9am.

That I should be able to make.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on September 19, 2013, 08:42:58 AM
I'm not sure if Sherman and/or Andy made it in time.

With rain and thunderstorms moving in, the demolition was moved to 8:30 AM. Which proved to be good timing, as latest radar shows Madison is getting hit pretty good.

EDIT TO ADD: Here's a screenshot of Radarscope on my iPod touch, centered on the Madison vicinity at 8:58. Remember, the original schedule would've meant this was 2 minutes before the blast.

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fi.imgur.com%2FvbCQmr3.jpg&hash=29bea5f0d9b09435414ec9e1c485309030757d7e) (http://imgur.com/vbCQmr3)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 19, 2013, 11:53:06 AM
I was three blocks away, parking.  Heard the boom, felt the whomp, and saw the ripples in the river, but the trees blocked my view of the bridge.  So close...

If I had tuned to the local FM station I probably would have known it was going to be close, but I don't think I could have improved my timing.

Just got back to work, so it only cost half a day.



Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on September 19, 2013, 04:04:55 PM
Quote from: andy on September 19, 2013, 11:53:06 AM
I was three blocks away, parking.  Heard the boom, felt the whomp, and saw the ripples in the river, but the trees blocked my view of the bridge.  So close...

If I had tuned to the local FM station I probably would have known it was going to be close, but I don't think I could have improved my timing.

Just got back to work, so it only cost half a day.

Nothing you could've done about it without possibly breaking a traffic law or two.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 19, 2013, 11:37:20 PM
I probably bent enough rules just getting there when I did.  I just didn't plan well enough, no one to blame but myself.

I checked the twitter about 7:30, but they hadn't announced the change in plans yet.  If I had also thought to turn off the MP3 and tune the local station (WORX FM 96.7), I could have at least gotten a less optimal view from down river (through the new bridge).  I think that might fit another thread about the benefit of listening to local stations.  Live, Learn...
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on September 20, 2013, 12:34:22 AM
Quote from: andy on September 19, 2013, 11:37:20 PM
I probably bent enough rules just getting there when I did.  I just didn't plan well enough, no one to blame but myself.

I checked the twitter about 7:30, but they hadn't announced the change in plans yet.  If I had also thought to turn off the MP3 and tune the local station (WORX FM 96.7), I could have at least gotten a less optimal view from down river (through the new bridge).  I think that might fit another thread about the benefit of listening to local stations.  Live, Learn...

Well, certainly you could've. I would argue that either way, the rain foricing the schedule change screwed with things. The change was not made public until 8:10 AM. Had the original plans gone ahead, you'd have made it with 20 minutes to spare. There was just too much lightning within the approaching storms, which could have caused a premature detonation of the blasting caps -- much too dangerous if there are personnel in the area including any traffic on the new bridge. Once the span was rigged up, which I believe they did overnight, they had to go with it.

I am interested to hear if there are any delays to salvage operations, because you can't put personnel in the water with lightning in the vicinity. It simply can't/shouldn't be done.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 20, 2013, 01:58:34 PM
I'm sure the lightning projections were a major concern.  I didn't hang around long and there were a couple of pretty big strikes before I got out of town. Maybe 20 minutes, certaintly before the scheduled 9:00 demolition.

Below are a couple of the official photos.  They don't show it, but there was a lot less of the debris above water than the past blasts, so that itself might make the recovery a bit more work.

Fortunately the blast have been staged so that between the two channels available, the river traffic is not too disturbed.

Also, it looks to me like this was a much more colorful blast than the others.  The blast masters are probably as dissapointed as the rest of us to have rushed the show and diminished the audience.

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fwww.miltonmadisonbridge.com%2Fwp-content%2Fuploads%2Fgallery%2Fseptember-2013%2Fcu-shot-1-madison-blast-4.jpg&hash=092b5d8b39800e16abe97a2faa4f4099d788c6be)

(https://www.aaroads.com/forum/proxy.php?request=http%3A%2F%2Fwww.miltonmadisonbridge.com%2Fwp-content%2Fuploads%2Fgallery%2Fseptember-2013%2Fgopro-3-madison-blast-4.jpg&hash=8c2563fb4c0c56496eb27376074302333ec1a16c)

Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on September 24, 2013, 05:04:41 PM
Now that the demolition is done, I don't know if I should return to the Ohio River thread on this topic.  But this one is fresher.

Now that the demolition is done, they are moving on to improving the piers and not are looking at a Mid-November slide for the new span;

http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=79136 (http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=79136)
QuoteNow that the old Madison-Milton bridge has been removed, workers have started widening and strengthening the existing piers that will support the new bridge superstructure. Work is progressing on Pier Two on the Milton side of the Ohio River. Each pier will be capped before the new bridge is slid from its temporary piers. The bridge slide is tentatively scheduled for mid-November
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on January 14, 2014, 09:25:53 PM
There's not been much reporting on the bridge progress, but it looks like they are getting closer to the big slide.

http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=81126 (http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=81126)
Quote1/14/2014 3:00:00 PM
WORK ON FINAL PIER CAP
A boom is used to fill the last pier cap mold for the new Madison-Milton bridge Monday. Once the concrete is cured and the cap set, plates will be installed for the bridge slide from the temporary piers. The slide is expected to be in mid-February, though many variables are at play, which will determine the actual date. Demolition of the old bridge pier near Madison is expected in the coming weeks. An official spokesman with the project said that a report at a recent Milton City Commission meeting stating that the first blast to the old pier would be today was not correct and that the blast will likely be next week. Before the blast, official notices - including any safety perimeters - will be sent to all media outlets and posted at the project's official website, www.miltonmadisonbridge.com. (Staff photos by Ken Ritchie/kritchie@madisoncourier.com)

Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on January 23, 2014, 11:20:23 PM
Another small step.  The final pier not being rehabilitated and used is about to be demolished.
The fall of the pier in the first stage demolition might make for a pretty big splash.

http://www.miltonmadisonbridge.com/wp-content/uploads/2014/01/pier5blastforweb1-22-14.pdf
QuoteThe 92-foot-tall pier will be removed in a series of two blasts scheduled to take place several days apart. Using controlled explosives, the first blast will topple the pier above the water line. A tension line anchored on the Madison side of the river will be used to pull the pier toward the shoreline, controlling the direction of its fall. Once the old pier is safely resting on the shoreline, it will be broken into smaller pieces and hauled off site. A second blast will fracture remaining portions of the pier under water so that they can be removed and hauled off.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on January 30, 2014, 05:43:00 PM
http://www.miltonmadisonbridge.com/wp-content/uploads/2014/01/Pier-blast-scheduled-for-January-31-at-44.pdf (http://www.miltonmadisonbridge.com/wp-content/uploads/2014/01/Pier-blast-scheduled-for-January-31-at-44.pdf)
QuoteIn preparation for the upcoming bridge slide, the only remaining original Milton-Madison Bridge pier is scheduled to be demolished Friday, January 31 at 4:00 p.m. Recent cold weather has hampered efforts to schedule the blast. Demolition will require a brief bridge closure lasting approximately 10 minutes.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on January 31, 2014, 10:48:14 PM
The pier was toppled today.  Prior to the demolition, the river landing was filled with dirt, so the big splash I was speculating about didn't happen. :-(

Video and a projection for a March slide on Youtube.
http://www.youtube.com/watch?v=rQMUNe6m6CI (http://www.youtube.com/watch?v=rQMUNe6m6CI)
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: JMoses24 on March 11, 2014, 05:36:49 AM
The slide is tentatively set to happen Friday...BUT there's a problem.

The bridge has been closed following a beam shifting on the bridge around 2 AM.

http://953wiki.com/local-article/milton-madison-bridge-emergency-closure-following-beam-shift/

QuoteMADISON, In. (WDRB) —  The Milton-Madison Bridge is shut down early today, after officials say a beam shifted and made the bridge unstable.

A resident who lives near the bridge told a Louisville TV station they heard a loud pop around 2 a.m. Tuesday. Police are blocking both ends of the bridge, as the structure is checked.

Kentucky State Police say the project manager notified them and requested help in setting up barricades.

The bridge was scheduled to close on Friday so crews could shift the bridge onto the refurbished piers. Crews estimate it will take 16 hours to slide the bridge over and another several days to secure it.

There is no information on when the bridge will reopen or how this development might affect the scheduled shift later this week. One word is that the bridge may be closed till after the slide.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on March 11, 2014, 12:17:50 PM
More information from the local paper;
http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=82181 (http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=82181)
QuoteOfficials closed the Madison-Milton bridge this morning after a worker was injured by a falling steel beam.

A steel bearing between the bridge and a pier dislodged, causing the injury, according to a joint statement released by Kentucky and Indiana transportation officials.

The worker, who was not identified, was taken to King's Daughters' Hospital, according to the news release. The worker was not seriously injured.

On the positive side, they also said;
Quote"They felt there was no issue keeping the river open,"
So I guess they don't think total failure is a concern.
Title: Re: Explosive Demolition at the Milton-Madison Ohio River Bridge
Post by: andy on April 02, 2014, 08:41:10 PM
I realize double posting is generally bad, but for those not following the resumption/continuation of this thread in the Ohio Valley region, the new bridge span is set to slide this weekend after a significant set back.

https://www.aaroads.com/forum/index.php?topic=3891.msg290238#msg290238 (https://www.aaroads.com/forum/index.php?topic=3891.msg290238#msg290238)

http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=82562 (http://madisoncourier.com/main.asp?SectionID=178&SubSectionID=964&ArticleID=82562)

http://www.miltonmadisonbridge.com/ (http://www.miltonmadisonbridge.com/)