The Antelope Wash section will be finished in a couple months. The SR 71 to SR 89 section is starting construction soon. The Carrow-Stephens section (search Google Maps for Gunsight Canyon, Arizona) is in design, and was scheduled for construction in FY2016 but got bumped tentatively to FY2023. The Cane Springs section is a 2016 design, and whenever they get money construction (probably FY2027 or later unless money starts raining from the sky). That leaves the east I-40 interchange, a couple miles on the north side of Wikieup, 20+ miles between the Santa Maria River and SR 71 (i.e. where the Joshua trees are), and whatever ends up happening with Wickenburg. It's good progress, but there's a lot of work to go, and no real plans on what will be done or when besides the handful of projects I just mentioned. Arizona is broke and everything that can be deferred is being deferred to free up money for pavement preservation, so it may be another 15 years before anything else gets rolling.