Albert

OR 42 project Adams to Finley: 2021 - Leveled parts of highway bypass (built 1990s) that are 6 ft. higher than level and restriped

Replaced some Curb ramps

East of Coquille: Highway ground, repaved, and restriped to include a Center Turn Lane

2022 - Replaced some more curb ramps and built a new pedestrian island

Already leveled, older bypass parts ground and repaved, then new overlay put on top of that and existing pavement and striped

Project completion - Sep. 2022