Few more pictures. Again, photos were taken Thursday, June 15, 2023, unless otherwise noted.
Although the focus of construction has generally shifted to Marion County, contractors
Crider & Crider and
Rieth Riley, among others, are still hard at work in Johnson County, finishing up Smith Valley Road overpass and interchange as well as paving long stretches of mainline between State Road 144 and Fairview Road. Another area where work is still ongoing is the SR 144 interchange and the mainline bridges over Bluff Creek just to the south.
I-69/State Road 144 interchange, Johnson County
At 8:15pm, a crew awaits the arrival of the truck bringing concrete to pour an approach slab section for the southbound bridge over Bluff Creek; looking southeast from the State Road 144 overpass.

View looking north from the SR 144 overpass using the long range lens. The thick haze nearly obscures the Smith Valley Road overpass in the deep background. On the left a paving crews is at work on the southbound right shoulder. In case you're wondering, the BGS in the middle-right reads:
Smith Valley Rd 2
I-465 10
Indianapolis 20

The paving crew at work about a quarter mile north of SR 144 overpass; looking west. It's unusual to shoot directly into the sun, but the thick summer haze, along with Canadian wildfire residue smoke, made it possible.

More signage, this time looking west toward the eastern roundabout at the I-69/SR 144 interchange.

Long range view looking south from the SR 144 overpass. Currently, all traffic in this vicinity is running on the northbound lanes. After the southbound paving completes, which will be soon, traffic will be shifted to the newly finished roadway. But it's not clear, to me, how four lanes of traffic will be maintained, as the southbound bridge over Bluff Creek appears just a bit too narrow. Three lanes, yes, four, hmm ... that's really a tight squeeze, if possible at all. Anyway, how MOT is managed when they seal off the northbound roadway to begin work to replace the northbound bridge over Bluff Creek will be, if anything, interesting. It's possible they'll just demo 3/4 of the northbound bridge, leaving one travel lane available.

Decorative element at the SR 144 overpass; looking west. Seems like a couple of huge planters for trees and bushes, but who knows.

Another view looking north from the SR 144 overpass. Yeah, guys, we know, it's been a long day.

Different perspective; looking south from the SR 144 overpass. Later, I noticed the crew busy with the concrete pour, but, alas, it was getting rather late for another stop.

One more shot looking north from the SR 144 overpass, with the shoulder paving crew on the left.

Closer look at the paving crew; looking west.