tolbs17

  • *
  • Offline Offline

  • Posts: 0
  • Age: 21
  • Location: Greenville, NC
  • Last Login: March 31, 2022, 07:24:24 PM
Re: Complete NC 540 Project
« Reply #200 on: January 01, 2022, 12:44:28 PM »

For any locals that want a good view of NC-540 construction, take a ride over to the Fanny Brown Rd. overpass. It has a really good vantage point in both directions. Also drove past the future Holly Springs Rd. interchange. The area is unrecognizable with the clear cutting of all the trees. Don't know how well a diverging diamond is going to work here given the thru traffic volumes on Holly Springs Rd. and the relocated Kildaire Farm Rd. intersection being just to the north.
Do not live in that area but I can imagine how far it has came when looking at this.

http://prntscr.com/25lizzj

Red is phase 1 movements guessed by me.

Blue is phase 2 movements.
Logged

tolbs17

  • *
  • Offline Offline

  • Posts: 0
  • Age: 21
  • Location: Greenville, NC
  • Last Login: March 31, 2022, 07:24:24 PM
Re: Complete NC 540 Project
« Reply #201 on: January 11, 2022, 06:24:02 PM »

Does anybody have a link that shows the signage plans of the southern extension of 540?

Btw, as seen in Q&A 13, this section will be paved with asphalt and not concrete.

https://www.ncdot.gov/projects/complete-540/Documents/complete-540-woodcreek-q&a.pdf
Logged

tolbs17

  • *
  • Offline Offline

  • Posts: 0
  • Age: 21
  • Location: Greenville, NC
  • Last Login: March 31, 2022, 07:24:24 PM
Re: Complete NC 540 Project
« Reply #202 on: February 06, 2022, 03:50:26 PM »

Definitely coming along nicely....

Logged

architect77

  • *
  • Offline Offline

  • Posts: 551
  • Location: Atlanta
  • Last Login: March 03, 2024, 08:13:14 PM
Re: Complete NC 540 Project
« Reply #203 on: February 06, 2022, 05:52:44 PM »

Thanks for posting the above links. Very interesting.
Logged

tolbs17

  • *
  • Offline Offline

  • Posts: 0
  • Age: 21
  • Location: Greenville, NC
  • Last Login: March 31, 2022, 07:24:24 PM
Re: Complete NC 540 Project
« Reply #204 on: February 06, 2022, 09:17:28 PM »

Thanks for posting the above links. Very interesting.
Yw.

Now I just wonder what's gonna happen with all the traffic coming from I-40 east wanting to jump on US-70 east. I feel like a full closure will probably be needed and a lot of traffic uses that ramp.
Logged

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #205 on: April 28, 2022, 11:20:05 AM »

Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

snowc

  • *
  • Offline Offline

  • Posts: 803
  • Age: 22
  • Last Login: May 20, 2022, 01:43:40 PM
Re: Complete NC 540 Project
« Reply #206 on: April 28, 2022, 11:58:13 AM »

Closures on Holly Springs Road and Kildaire Farm Road this weekend.

https://www.ncdot.gov/news/press-releases/Pages/2022/2022-04-closure-holly-springs-road-and-kildaire-farm-road.aspx
Its about time! NC 540's comin along nice!
That means that the girders will be installed, right, on Exit 50, or have they already?  :hmmm:
Logged

cowboy_wilhelm

  • *
  • Offline Offline

  • Posts: 348
  • Location: Raleigh
  • Last Login: March 16, 2024, 12:10:54 PM
Re: Complete NC 540 Project
« Reply #207 on: May 04, 2022, 08:29:56 PM »

Here are some mediocre photos of the interchange going eastbound from I-40 to US-70.




Logged

NJRoadfan

  • *
  • Offline Offline

  • Posts: 1815
  • Location: New Jersey
  • Last Login: March 18, 2024, 10:30:29 PM
Re: Complete NC 540 Project
« Reply #208 on: June 20, 2022, 04:18:18 PM »

Updated flyover video of progress:
Logged

kendallhart808

  • *
  • Offline Offline

  • Posts: 23
  • Location: North Carolina
  • Last Login: March 16, 2024, 10:50:29 AM
Re: Complete NC 540 Project
« Reply #209 on: June 20, 2022, 07:42:59 PM »

Updated flyover video of progress:
Given how it looks at I-40, I was honestly under the impression it was further along than that.
Logged

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #210 on: June 23, 2022, 01:50:50 PM »

Speaking of that interchange, the ramp from US-70 West to I-40 East will be permanently closed on July 6.

https://www.ncdot.gov/news/press-releases/Pages/2022/2022-06-23-us-70-i-40-loop-ramp-clayton-closed.aspx
Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #211 on: July 01, 2022, 04:57:58 PM »

Deerborn Drive extension is expected to open around July 6. Meanwhile, around July 11, Deer Meadow Drive is expected to close for about a year.

https://www.ncdot.gov/news/press-releases/Pages/2022/2022-07-01-complete-540-deerborn-drive-extension.aspx
Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #212 on: July 15, 2022, 02:27:12 PM »

Upcoming traffic shift on Bells Lake Road, which is expected to last for a year.

https://www.ncdot.gov/news/press-releases/Pages/2022/2022-07-15-bells-lake-traffic-shift-complete-540.aspx
Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

Evan_Th

  • *
  • Offline Offline

  • Posts: 505
  • Location: United States
  • Last Login: March 12, 2024, 02:57:54 PM
    • Papyrus Rampant
Re: Complete NC 540 Project
« Reply #213 on: July 15, 2022, 05:52:21 PM »

Wild idea:  Maybe this section of 540 should be co-signed with I-42?
Logged

WashuOtaku

  • *
  • Offline Offline

  • Posts: 674
  • Location: North Carolina
  • Last Login: March 15, 2024, 04:23:49 PM
Re: Complete NC 540 Project
« Reply #214 on: July 15, 2022, 06:24:20 PM »

Wild idea:  Maybe this section of 540 should be co-signed with I-42?

Hard Pass. Also, NC 540 will be a toll road here.
Logged

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #215 on: July 16, 2022, 09:42:55 AM »

Wild idea:  Maybe this section of 540 should be co-signed with I-42?

Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #216 on: July 21, 2022, 01:11:12 PM »

On or around July 25, a section of Pierce Olive Road will be closed for 8 months.

https://www.ncdot.gov/news/press-releases/Pages/2022/07-21-2022-temporary-closure-pierce-olive-c540.aspx
Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

maxkil123

  • *
  • Offline Offline

  • Posts: 2
  • Location: Raleigh, NC
  • Last Login: March 18, 2024, 05:58:54 PM
Re: Complete NC 540 Project
« Reply #217 on: August 19, 2022, 07:51:21 PM »

Does anyone know what happened to Rick Williamson?  I check his profile for videos regarding the NC 540 project, but his profile and videos are no longer on YouTube.
Logged

bob7374

  • *
  • Offline Offline

  • Posts: 1973
  • Age: 59
  • Location: East Weymouth, Massachusetts
  • Last Login: March 16, 2024, 11:11:09 AM
    • Bob Malme's Road Pages
Re: Complete NC 540 Project
« Reply #218 on: September 26, 2022, 06:08:05 PM »

NCDOT has some progress to report with the Complete NC 540 project:
https://www.ncdot.gov/news/press-releases/Pages/2022/2022-09-26-c540-opening-holland-church-rd.aspx

cowboy_wilhelm

  • *
  • Offline Offline

  • Posts: 348
  • Location: Raleigh
  • Last Login: March 16, 2024, 12:10:54 PM
Re: Complete NC 540 Project
« Reply #219 on: November 28, 2022, 05:29:19 PM »

It appears that the last leg of the Triangle Expressway from I-40 to US 64 has been accelerated. The two projects (R-2829 A & B) have been added to the 12-month let list as "strategic lettings," and a design-build RFQ went out 11/15 for section B. Section B (the northern part) will be let 7/18/2023 and Section A will follow 9/19/2023, both as design-build contracts. The project website currently shows an estimated contract letting in 2025.

Complete 540 Phase 2 Industry Forum Presentation
Logged

Henry

  • *
  • Offline Offline

  • Posts: 8478
  • Age: 53
  • Location: Chicago, IL/Seattle, WA
  • Last Login: March 18, 2024, 10:22:35 PM
    • Henry Watson's Online Freeway
Re: Complete NC 540 Project
« Reply #220 on: November 29, 2022, 07:27:34 PM »

When the whole loop is completed, will the eastern end of I-540 continue to be at US 64/US 264 (Future I-87)? I still find it strange that it wasn't planned as I-640 in the first place, but let's make it the last time this is brought up.
Logged
Go Cubs Go! Go Cubs Go! Hey Chicago, what do you say? The Cubs are gonna win today!

wdcrft63

  • *
  • Offline Offline

  • Posts: 963
  • Location: Durham, NC
  • Last Login: March 15, 2024, 05:40:28 PM
Re: Complete NC 540 Project
« Reply #221 on: November 29, 2022, 07:39:45 PM »

When the whole loop is completed, will the eastern end of I-540 continue to be at US 64/US 264 (Future I-87)? I still find it strange that it wasn't planned as I-640 in the first place, but let's make it the last time this is brought up.
Quick answer: yes.
Logged

LM117

  • *
  • Offline Offline

  • Posts: 3289
  • Age: 34
  • Location: Danville, VA 👎
  • Last Login: March 08, 2024, 03:36:52 PM
Re: Complete NC 540 Project
« Reply #222 on: November 30, 2022, 08:13:23 AM »

When the whole loop is completed, will the eastern end of I-540 continue to be at US 64/US 264 (Future I-87)? I still find it strange that it wasn't planned as I-640 in the first place, but let's make it the last time this is brought up.

As mentioned above me, yes. Also, back in early 2013 when NCDOT requested the I-495 designation for what is now I-87, they asked FHWA for a waiver to keep the I-540 number as is, which was granted.
Logged
“I don’t know whether to wind my ass or scratch my watch!” - Jim Cornette

architect77

  • *
  • Offline Offline

  • Posts: 551
  • Location: Atlanta
  • Last Login: March 03, 2024, 08:13:14 PM
Re: Complete NC 540 Project
« Reply #223 on: December 02, 2022, 09:58:35 PM »

When the whole loop is completed, will the eastern end of I-540 continue to be at US 64/US 264 (Future I-87)? I still find it strange that it wasn't planned as I-640 in the first place, but let's make it the last time this is brought up.

As mentioned above me, yes. Also, back in early 2013 when NCDOT requested the I-495 designation for what is now I-87, they asked FHWA for a waiver to keep the I-540 number as is, which was granted.
I'm holding out hope that the completed loop will be renamed.

Not many people even understand the meaning behind the number designation, but an even first number would be better suited for a complete loop.

I would like to place a wager that eventually be renamed. When the bonds are paid off, why wouldn't it all become one interstate designation?
Logged

sprjus4

  • *
  • Offline Offline

  • Posts: 8829
  • Location: Hampton Roads, VA
  • Last Login: Today at 01:46:42 AM
Re: Complete NC 540 Project
« Reply #224 on: December 02, 2022, 10:06:45 PM »

^ No, a renumber would just cause more confusion than needs to exist. The highway has existed for 30+ years as “540”  and will stay that.
Logged

 


Opinions expressed here on belong solely to the poster and do not represent or reflect the opinions or beliefs of AARoads, its creators and/or associates.