TDOT's latest on this project- From Leipers Creek Road to Columbia Pike (SR 6):
The grading work and bridge construction on this project is complete. However, the project still needs to be paved, striped, signed and have guardrail installed. Lojac Enterprises will begin this work in early 2012.
Since paving is well underway on this segment, it could be eligible to open soon. Even so, the part from Carter's Creek Pike to Leipers Creek Road will be closed as Carter's Creek Pike (TN 246) is the only new exit on the unfinished 12 miles.
- From Pinewood Road (SR 46) to Leipers Creek Road:
Eubank Asphalt Paving & Sealing began work on this section in early 2010. This contract includes grading, bridge and retaining wall construction, paving, striping, signing and installation of guardrails.
Even a month or two ago, there was still unfinished grading and unfinished bridges along this section.