KDOT Contract Lettings - Updated Monthly since April 2015.

Started by route56, April 10, 2015, 11:23:31 AM

Previous topic - Next topic

route56

#250
August and September lettings updated with awarded bids announced on October 7.
Peace to you, and... don't drive like my brother.

R.P.K.


route56

#251
Approved Bids Announced 12/10/20

November, 2020

Federal-Aid:

59-3 KA-5885-01: 1.50 HMA overlay from the Jefferson/Atchison county line to the south city limits of Atchison. Herzog Contracting Corp., St. Joseph, Missouri, $1,795,474.96.

36-7 KA-6005-01: Pavement marking on US 36 in Brown County. Through Fairview, US 36/1st Street to be re-striped from 4 lanes to 3.
36-22 KA-6004-01: Pavement marking from the Brown/Doniphan county line east approximately 3000 feet.

Bids Rejected or no bid received - Re-let January 2021

50-9 KA-5887-01: Milling and HMA overlay from the Marion/Chase county line east 9 miles, and from the Simmons Creek bridge east to K-177. APAC-Kansas Inc Shears Division, Hutchinson, Kansas, $2,747,855.04.

14 C 4987-01: Pavement marking on major collector roads in Clay County. Century Fence Co., Pewaukee, Wisconsin, $550,028.95.

15-21 KA-5851-01: Milling and HMA overlay from the Marion/Dickinson county line to the south city limits of Abilene APAC-Kansas, $2,891,255.48.

24-62 KA 3950-01: Replace the Brown's Creek bridge 7.61 miles east of K-128. Traffic to be carried through on a shoo-fly detour. King Construction Company Inc. & Subsidiaries, Hesston, Kansas, $1,948,530.57.

24-62 KA 3963-01: Replace the Mulberry Creek bridge, 11.15 miles east of K-128. Traffic to be carried through on a shoo-fly detour. King, $2,090,417.57.

83-55 KA-5884-01: 2-inch HMA overlay from the Scott/Logan county line to US 40. APAC-Kansas, $5,434,727.00.

54-1 KA 3913-01: Replace the bridge over the UP Parsons Subdivision on the east side of Moran and reconstructing the approaches. Detour via US 59, K-31, and K-3. A M Cohron & Son Inc., Atlantic, Iowa, $3,703,814.47.

7-11 KA-6032-01: Pavement marking from US 69 to the Cherokee/Crawford county line. Century Fence, $299,575.00.

50-78 KA-5829-01: Milling and HMA overlay from the east end of the 4 lane freeway near Hutchinson to the Reno/Harvey county line. APAC-Kansas, $2,940,894.45.

28 C 4971-01: Major collector signing and pavement marking in Finney County. Roadsafe Traffic Systems Inc., El Dorado, Kansas, $425,863.39.

156-28 KA-5852-01: Milling and HMA overlay on K-156 from Garden City to K-23. APAC-Kansas, $3,738,125.94.

50-28 KA-5886-01: Milling and HMA overlay from Garden City to the Finney/Ford County line. APAC-Kansas, $2,775,601.89.

86 TE 0485-01: Rail-trail construction from Alice Avenue to 6th Street in Scott City RFB Construction Company, Inc., Pittsburg, Kansas, $297,796.02.

81-96 KA 4530-03: Grading, Flood Repair, and Riverbank Stabilization on the east bank of the Ninnescah River adjacent to US 81, located 1.4 miles north of the US 81/K-55 junction near Belle Plaine. Dondlinger & Sons Construction Co. Inc., Wichita, Kansas, $1,018,065.00.

Non-FA:

24-52 KA-5883-01: Milling and HMA overlay from K-16 in Tonganoxie to the Leavenworth/Wyandotte county line. Bettis Asphalt & Construction Inc., Topeka, Kansas, $3,648,825.09.

32-106 KA-5868-01: 2-inch surface recycle from US 24-40 to Bonner Springs. Bettis, $2,105,399.69.

159-106 KA-5880-01: Milling and HMA overlay on US 159 from Effingham to Horton. Herzog, $1,891,827.07

244-31 KA-6030-01: Crack sealing along the entire length of K-244. Pavement Pro's LLC, McPherson, Kansas, $33,639.00.

9-106 KA 5861-01: 2-inch surface recycle and chip seal from Concordia to Clifton in Clay and Washington counties. Dustrol Inc., Towanda, Kansas, $1,627,361.80.

15-106 KA-5865-01: Milling and HMA overlay from K-18 to Clay Center in Dickinson and Clay counties. APAC-Kansas, $3,127,500.17.

179-39 KA-6029-01: Crack sealing along the entire length of K-179. Pavement Pro's, $47,422.12.

160-94 KA-5840-01: Milling and HMA overlay from the Colorado state line to Johnson City. APAC-Kansas, $1,809,807.21.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#252
Approved bids announced 1/7/21
Approved bid announced 2/5/21

December 2020

There is a total of 30 projects in the December lettings, most of which are maintenance projects

Federal-Aid:

24-15 KA 3239-02: Culvert reconstruction/widening, mill/overlay, and signage replacement on US 24 from 2 miles west of Miltonvale to the Cloud/Clay county line. Ebert Construction Co Inc & Subsidiary, Wamego, Kansas, $7,026,598.82.

70-84 KA-5687-01: Repair of bridges 70-84-23.05 and 70-84-24.59 on Westbound I-70 near Dorrance. Wildcat Construction Co. Inc. & Subsidiaries, Wichita, Kansas, $428,899.19.

106 KA 4746-02: Signage replacement on US 281 from the Barton/Russell County Line to 15th Street in Russell, US 281 from the West Junction with K-18 to the Russell/Osborne County line, K-18 from US 281 to the Russell/Lincoln County line, and K-232 from the Lincoln/Russel County line to K-18. KOMO Construction LLC / DBA A&H CO., Lakeville, Minnesota, $184,500.00

70-106 KA 4746-04: Signage replacement on I-70 in KDOT District 3 not previously covered by previous signage replacement projects. This does not include any exit guide sings (BGS). Martin Outdoor Enterprises Inc., Pittsburg, Kansas, $796,258.61.

31-02 KA 3907-01: Replacement of Bridge #030 (North Fork Little Osage Drainage) east of Kincaid. Traffic to be carried through the project via a shoo-fly detour. WCl, Inc., Paola, Kansas, $1,499,098.77

3-6 KA-5922-01: 1-inch surface recycle and micro surfacing from K-39 to US 54. Dustrol Inc., Towanda, Kansas, $868,507.73.

54-6 KA-5936-01: Surface recycling and ultrathin bonded asphalt surfacing from the Allen/Bourbon county line to US 69. APAC-Central, Inc., Fayetteville, Arkansas, $2,753,205.53.

103-11 KA-5940-01: 1.5-inch milling and 1.5-inch HMA overlay along the entire route of K-103 APAC-Central, $718,523.75.

99-37 KA-5939-01: 1-inch milling and 1-inch HMA overlay from US 54 to the Greenwood/Lyon county line. Shilling Construction Co. Inc., Manhattan, Kansas, $1,513,389.00.

7-54 KA-5932-01: 1.5-inch milling and 1.5-inch HMA overlay from K-52 north to K-152. Shilling, $1,810,782.40.

166-63 KA-5942-01: 1-inch milling and 1-inch HMA overlay from the South Junction with US 75 near Caney to the west city limits of Coffeyville. Cornejo & Sons LLC,
Wichita, Kansas, $1,719,972.65.


54-76 KA 5429-01: Reconstruction of a two-block section of 1st Street from New Street to Mound Street in Pratt from 9-inch concrete with earth base to 11-inch concrete with a gravel base. Two lanes of traffic to be maintained through the work zone. Vogts Parga Construction LLC, Newton, Kansas, $744,409.18

25-34 KA-5826-01: 1-inch milling and 2-inch HMA overlay from the north city limits of Ulysses to the Grant/Kearney county line. Venture Corporation, Great Bend, Kansas, $1,508,207.82.

27-36 KA-5930-01: 2.0-inch milling and ultrathin bonded asphalt surface on K-27 in Greeley County, with the exception of the section through Tribune. Venture, $4,394,345.52.

283-42 KA-5870-01: 1-inch milling and 2-inch HMA overlay from the Ford/Hodgeman county line to the south city limits of Jetmore
156-42 KA-5869-01: 1-inch milling and 1.5-inch HMA overlay from the east city limits of Jetmore to the Hodgeman/Pawnee county line (non-FA) Venture, $4,539,465.64.

50-47 KA-5935-01: 1.5-inch milling and 1.5-inch HMA overlay from the east city limits of Lakin to the Kearny/Finney county line. Venture, $1,446,061.80.

56-65 KA-5833-01: 2-inch milling and 2-inch HMA overlay from the Oklahoma/Kansas state line to the west junction with K-51. APAC-Kansas Inc. Shears Division, Hutchinson, Kansas, $3,111,001.46.

Non-FA:

105 KA-5953-01: Full-depth patching, 1.5-inch milling, 1.5-inch HMA overlay, and Mastic surface treatment on the shoulders on K-7 from the Kansas River bridge to the concrete pavement north of Elizabeth Street in Bonner Springs. J M Fahey Construction Company, Grandview, Missouri, $1,884,737.81.

75-63 KA-5948-01: 2-inch milling and 2-inch HMA overlay on US 75 in Caney. Cornejo & Sons, $352,388.35.

63 KA-5950-01: Concrete pavement patching on the 4-lane segment of US 75/US 400 in northern Montgomery County. Emery Sapp & Sons Inc. And Subsidiaries, Columbia, Missouri, $1,159,593.20.

106 KA-5924-01: 1-inch milling and 1-inch HMA overlay on K-3 from K-31 south to K-65, the entire length of K-65 from K-3 to K-31, and K-31 from K-65 to the east junction with K-7. Shilling, $1,464,616.60.

54-106 KA-5944-01: 3-inch milling and 2-inch HMA overlay from the west junction with K-99 to US 75 in Greenwood and Woodson Counties. Shilling, $4,695,119.26.

56-106 KA-6041-01: Asphalt crack sealing on US 56 from Ellinwood to Lyons in Barton and Rice Counties. Mission Construction Co. Inc., St. Paul, Kansas, $99,810.78.

14-106 KA-6044-01: Asphalt crack sealing on K-14 from US 160 to K-42 in Harper and Kingman Counties. Scodeller Construction Inc., Wixom, Michigan,
$94,929.92.


49-106 KA-6048-01: Crack Sealing on K-49 from 2 miles north of US 160 to K-42 in Sumner and Sedgwick Counties. Mission, $217,825.50.

53-96 KA-6047-01: Crack sealing along the entire length of K-53. Mission, $86,823.50.

56-106 KA-5843-01: 1-inch milling and 1.5-inch HMA overlay from K-190 near Satanta to Montezuma in Haskell and Gray Counties. Venture, $4,143,694.44.

144-106 KA-5847-01: 2-inch milling and chip sealing along the entire length of K-144 in Haskell and Grey counties. Dustrol, $1,338,066.98.

34-106 KA-5858-01: 1.5-inch milling and 1.5-inch HMA overlay along the entire length of K-34 in Clark and Ford counties. Venture, $2,698,092.96.
Peace to you, and... don't drive like my brother.

R.P.K.

J N Winkler

Quote from: route56 on November 21, 2020, 02:22:52 PM70-106 KA 4746-04: Signage replacement on I-70 in KDOT District 3 not previously covered by previous signage replacement projects. This does not include any exit guide signs (BGS)

Don't miss the Superman reference on one of the typical installation sheets (page 3 of 236 in the plans PDF).
"It is necessary to spend a hundred lire now to save a thousand lire later."--Piero Puricelli, explaining the need for a first-class road system to Benito Mussolini

Scott5114

Quote from: J N Winkler on November 22, 2020, 01:16:21 PM
Quote from: route56 on November 21, 2020, 02:22:52 PM70-106 KA 4746-04: Signage replacement on I-70 in KDOT District 3 not previously covered by previous signage replacement projects. This does not include any exit guide signs (BGS)

Don't miss the Superman reference on one of the typical installation sheets (page 3 of 236 in the plans PDF).

uncontrollable freak sardine salad chef

route56

#255
Approved bids announced 2/5/21

The inauguration of President-elect Biden is not the only thing scheduled for January 20. It will also be the scheduled day for the monthly KDOT lettings. Included in the January lettings are several bridge replacements and signage upgrades, as well as a new roundabout in Kansas City

January 2021:

Federal-Aid:

116-3 KA 3883-01: Bridge replacement on K-116 west of Cummings. Detour via US 159 and US 59. Pfefferkorn & Drury Construction LLC, Olathe, Kansas, $756,191.35.

36-7 KA-6005-01: Pavement marking on US 36 in Brown County. Through Fairview, US 36/1st Street to be re-striped from 4 lanes to 3.
36-22 KA-6004-01: Pavement marking from the Brown/Doniphan county line east approximately 3000 feet. <em>(2nd attempt at letting for both projects)</em> Century Fence Co., Pewaukee, Wisconsin, $371,225.06

56-46 KA-5937-01: 3.0-inch HMA overlay from old 56 to I-35. Superior Bowen Asphalt Company LLC, Kansas City, Missouri, $1,288,763.57.

69-46 KA-5965-01: Ultrathin bonded asphalt surfacing from the Miami/Johnson county line to the Blue Valley Parkway. Superior Bowen, $1,423,918.35.

35-46 KA-6051-01/35-105 KA-6052-01: Pavement marking from I-435 to the Missouri state line.

32-52 KA 5176-01: Add left- and right-turn lanes on K-32 at the intersection with 222nd Street/Leavenworth County Route 1. Amino Brothers Company Inc., Kansas City, Kansas, $910,004.33.

9-58 KA-5934-01: 2.5-inch milling and 2-inch HMA overlay from US 77 to K-99. Hall Brothers Inc., Marysville, Kansas, $1,722,402.66.

31-70 KA 5964-01: 1-inch milling and 1-inch HMA overlay from I-35 to US 75
131-16 KA-5941-01: 1-inch HMA overlay along the entire length of K-131 from Lebo to I-35
Killough Construction Inc., Ottawa, Kansas, $889,787.67.

24-75 KA 3921-01: Replace the eastbound US 24 bridge over Blackjack Creek north of St. George. Traffic to be carried head-to-head on the westbound bridge. King Construction Company Inc. & Subsidiaries, Hesston, Kansas, $1,975,971.36.

105 N 0701-01: Construction of a roundabout at the intersection of 110th Street and Riverview Road in KCK. The design speed for the roundabout is 30 MPH. Kings Construction Co. Inc., Oskaloosa, Kansas, $2,859,272.83.

81-15 KA 5414-01: Full-depth reconstruction of the outside (right) lane of southbound US 81 from the South City Limits of Concordia to College Drive

106 KA 4745-02: Signage replacement on K-4 from the Rice/Ellsworth county line to Gypsum, along with K-141 and K-104. Signs Up LTD DBA Haren's Trees and Critters, Webster City, Iowa, $185,032.28.

106 KA 4746-01: Signage replacement on non-interstates in Sherman County (US 24B, K-27, K-253, and K-267) Signs Up LTD, $75,066.60.

70-98 KA-5686-01: Bridge repair on eastbound I-70 over K-198 near Collyer. Bridges Inc., Newton, Kansas, $249,251.95.

39-6 KA 3910-01: Replace the bridge over Pawnee Creek just west of the junction with K-7. Detour via K-3, K-47, and K-7. B & B Bridge Company LLC, St. Paul, Kansas, $1,389,580.52

99-10 KA 5411-01: Adding paved shoulders on K-99 from US 166B to the Chautauqua/Elk County line. Construction to be done in one-lane segments with one lane of traffic carried through controlled by stoplights. Cornejo & Sons LLC, Wichita, Kansas, $8,037,094.12.

160-11 KA 3904-01: Replace Bridge #050 on US-160, located 0.94 miles east of the Labette County line. Traffic to be carried through using a shoo-fly detour. B & B Bridge Company, $1,857,653.48.

166-11 KA 3905-01: Replace 5 bridges within 3 miles east of the Labette/Cherokee County line. Bridges Inc., $14,840,060.71.

19 TE 0475-01: Safe routes to school sidewalk construction in Girard

99-37 KA 3911-01: Replace the Fall River bridge on K-99 southeast of Eureka. Traffic to be carried through on a shoo-fly detour. Bridges Inc., $3,796,175.77.

166-63 KA-5685-01: Repair on the Onion Creek bridge west of Coffeyville. PBX Corporation & Subsidiary, Sapulpa, Oklahoma, $63,593.05.

146-67 KA-5966-01: 0.5-inch milling and 1.5-inch HMA overlay from US 59 to the Neosho/Labette county line. Heckert Construction Company Inc., Pittsburg, Kansas, $1,002,581.24.

169-106 KA 3255-01: Reconstruction of US 169 from 140th Road in Neosho County south of Chanute to 1150 Road in Allen County. Detour via K-39, US 75, and either K-47 or US 54. <em>(2nd attempt at this letting)</em> Emery Sapp & Sons Inc. and Subsidiaries, Columbia, Mo., $32,606,312.46.

400-8 KA-5689-01: Bridge repair on the Little Walnut River bridge east of Leon. Dondlinger & Sons Construction Co. Inc., Wichita, Kansas, $566,136.35.

177-8 KA-5691-01: Repair the bridge over the east arm of El Dorado Lake Dondlinger & Sons, $733,769.90.

87 N 0694-01: Reconstruction of Main Street from Grand Avenue to the Big Ditch in Haysville. Cornejo & Sons, $1,335,869.01.

106 KA 4748-01: Signage replacement on US 54, US 83, and US 400 in Kiowa County. Signs Up LTD, $155,074.25.

106 KA 4748-02: Signage replacement on K-1 and US 160 in Comanche County. Signs Up LTD, $146,657.40.

27-38 KA 3271-01: Reconstruction of K-27 from the south city limits of Syracuse north to US 50. Venture Corporation, Great Bend, Kansas, $6,512,961.85.

Non-FA:

56 KA-5978-01: 2.5-inch milling and 2-inch HMA on US 56 in Lyon County, along with the K-78 spur. Shilling Construction Co. Inc., Manhattan, Kansas, $3,247,356.00.

75-89 KA 5629-01: Lighting upgrade on US 75 at the bridge over the Kansas Turnpike. Phillips Southern Electric Company Inc., Wichita, Kansas, $59,450.00.

4-106 KA-5956-01: 2.5-inch milling and 2-inch HMA overlay on K-4 from US 24 to K-92. Hamm Inc., Perry, Kansas, $2,044,847.07.

16-106 KA-5959-01: 2.5-inch milling and 2-inch HMA overlay on K-16 from US 77 to K-99

73-105 KA 5891-01: Replace a damaged sign truss at the K-7/State Avenue interchange. Fulsom Brothers, Inc., Cedar Vale, Kansas, $223,491.83.

77-106 KA-6033-01: Chip Seal on US 77 from K-209 near Woodbine to the beginning of the concrete pavement south of I-70 near Junction City. Circle C, $468,947.51.

101 KA-6037-01: Chip seal on K-148 from US 36 to the Nebraska state line, along with K-234 and K-243. Circle C Paving and Construction LLC, Goddard, Kansas, $343,857.58.

19 KA-5967-01: 1.5-inch milling and 1.5-inch HMA overlay on US 69 from the Cherokee/Crawford county line to US 69B south of Arma, and on US 69B through Arma. Heckert, $2,301,696.48.

77-8 KA-6028-01: Scrub seal and chip seal on US 77 from the Cowley/Butler county line to 1/3 mile south of the Walnut River bridge.
Peace to you, and... don't drive like my brother.

R.P.K.

J N Winkler

I think the January 2021 letting may set a record for pure signing contracts in a single KDOT letting--I count four signing & delineation (non-freeway) and one sign truss replacement.  The KDOT project numbers for the first four (KA-4745-02, KA-4746-01, KA-4748-01, and KA-4748-02) also come out of the same KA-474X-XX block as a number of other pure signing contracts in recent lettings.
"It is necessary to spend a hundred lire now to save a thousand lire later."--Piero Puricelli, explaining the need for a first-class road system to Benito Mussolini

route56

Quote from: J N Winkler on December 21, 2020, 09:29:13 PM
I think the January 2021 letting may set a record for pure signing contracts in a single KDOT letting--I count four signing & delineation (non-freeway) and one sign truss replacement.  The KDOT project numbers for the first four (KA-4745-02, KA-4746-01, KA-4748-01, and KA-4748-02) also come out of the same KA-474X-XX block as a number of other pure signing contracts in recent lettings.

There's also major signage work included with the US 169 reconstruction (which, BTW, was originally scheduled for letting in October. I don't know if KDOT received no approvable bids or if they simply re-scheduled.)
Peace to you, and... don't drive like my brother.

R.P.K.

Scott5114

73-105 KA 5891-01 includes the full-on specifications for the standard Kansas truss gantry, which is fascinating, since I've always liked the design of it. However, I have an engineering question–the plans show the truss sections being bolted together as kind of an arch with the high point at the middle, which is described as "camber". Obviously, this arch is not obvious on an installed gantry. Is this upward arch to compensate for the weight of the signage, so that the panels will cause the gantry to sag in the middle, and appear to be level when under load? Or is this arch simply exaggerated in the plan sheets and is so small that it's not noticeable to the naked eye from ground level?
uncontrollable freak sardine salad chef

J N Winkler

Quote from: Scott5114 on December 22, 2020, 05:47:08 PMHowever, I have an engineering question–the plans show the truss sections being bolted together as kind of an arch with the high point at the middle, which is described as "camber". Obviously, this arch is not obvious on an installed gantry. Is this upward arch to compensate for the weight of the signage, so that the panels will cause the gantry to sag in the middle, and appear to be level when under load? Or is this arch simply exaggerated in the plan sheets and is so small that it's not noticeable to the naked eye from ground level?

Taking your questions in order:  Yes, and camber is also a feature of bridge girders.  Yes, I believe the plan sheets exaggerate somewhat--I've never seen it that obvious on a brand-new truss prior to installation of signs.
"It is necessary to spend a hundred lire now to save a thousand lire later."--Piero Puricelli, explaining the need for a first-class road system to Benito Mussolini

route56

December lettings have been updated with approved bids that have been announced today.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#261
February 2021

Approved bids announced 3/10/21

Included in the February lettings are two major construction projects in south-central Kansas.

Federal-Aid:

75-7 KA 4798-03: Create a new passing lane on US 75 by widening a 2.4-mile stretch to 4 lanes, starting at 3.2 miles north of K-20. This also includes widening the bridge over Plum Creek from 2 lanes to 4. Hamm Inc., Perry, Kansas, $7,979,818.90.

75-43 KA 4798-02: Create a new passing lane on US 75 near Netawaka by widening a 1.8-mile segment to 4 lanes. The project also includes updating the signs at the US 75/K-9 junction just north of the main project. Hamm, $3,964,876.39.

16-43 KA 5963-01: 1-inch milling and 1.5-inch HMA overlay on K-16 from Holton to the Jackson/Jefferson county line. K-16 in Holton and at the K-16/K-116 junction is to be milled to 1.5 inches. Herzog Contracting Corp., Saint Joseph, Missouri, $1,490,802.19.

7-46 KA 5692-01: Repairing the bridges taking 67th Street/Shawnee Mission Parkway over K-7. The ramp from Northbound K-7 to westbound 67th Street and from Southbound K-7 to Shawnee Mission Parkway is to be closed during part of this project. PCI Roads, LLC, Saint Michael, Minnesota, $1,190,308.01.

99-58 KA 3925-01: Replace a culvert with a bridge on K-99 near the intersection with Vista Road south of Frankfort. Traffic to be carried through on a shoo-fly detour. L & M Contractors Inc., Great Bend, Kansas, $1,957,821.62.

77-58 KA 5947-01: 2.5-inch milling and 2-inch overlay on US 77 from the west junction with US 36 west of Marysville north to the Nebraska state line.
233-58 KA 6078-01: 2.5-inch milling and 2-inch overlay along the entire length of K-233.
Hall Brothers Inc., Marysville, Kansas, $2,408,852.94.

56-70 KA 5938-01: 2.5-inch milling and 2-inch overlay on US 56 from the south junction with K-31 to the Osage/Douglas county line (presumably excluding the brick portion in downtown Burlingame) Hamm, $4,162,205.46.

24-89 KA-3235-01: 2.5-inch milling and 2.5-inch overlay on US 24 from Silver Lake to Menoken. Hamm, $1,174,284.66.

80-14 KA 3957-01/80-14 KA 3965-01: Replace two bridges over Dry Creek. L & M, $3,170,522.92.

81-72 KA 5679-01: Repair a bridge on US 81 south of Minneapolis. PCI Roads, $294,314.25.

106 KA 4745-01: Signage upgrade on the highways in Marion County and the Herrington area. It includes replacing the roundabout signage at the US 50/US 77 junction near Florence, but *not* at the US 56/US 77 junction near Marion. CC & I Engineering Inc./DBA Compass Consultants, Perham, Minnesota, $385,106.80.

148-101 KA 3956-01: Replace three bridges in a 7 mile stretch of K-148 in Washington County. Detour via US 81, US 36, and K-15. King Construction Company Inc & Subsidiaries, Hesston, Kansas, $3,073,397.77.

26 C 4978-01: Installation of "No Passing Zone" signs on the secondary roads of Ellis County. CC & I, $66,486.35.

35-70 KA 5693-01: Repair of the bridge carrying old US 75 over I-35. Bettis Asphalt & Construction Inc., Topeka, Kansas, $187,095.62.

106 KA 4747-01: Signage replacement on US 59, US 160, US 166, and K-101 in Labette County. CC & I, $275,566.28.

160-18 KA 5421-01: Reconstruction of 9th Avenue/US 160 in Winfield from College Street to Wheat Road. Cornejo & Sons LLC, Wichita, Kansas, $1,649,177.47.

14-78 KA 1007-02 and 14-80 KA 1007-03: The "Northwest Passage:" construction of a new super-two freeway, bypassing Nickerson and Sterling. Bob Bergkamp Construction Co. Inc., Wichita, Kansas, $81,749,251.37

235-87 KA 3232-03: Wichita North Junction Phase 2A: Replace the loop ramp from northbound I-135 to southbound I-235 with a two-lane flyover.
[The construction estimate is $30.2 million in 2020 dollars.] Dondlinger & Sons Construction Co. Inc., Wichita, Kansas, $36,319,409.09.

106 KA 5893-01: Signage replacement on K-4, K-23, and K-96 in Lane County. CC & I, $80,533.11.


Non-FA:

73-106 KA 5971-01: 2-inch mill and 2-inch Overlay on US 73/K-7 from Millwood Road in Northern Leavenworth County to the south city limits of Atchison. Herzog, $2,154,541.90.

181-71 KA 5153-01: Reconstruction of Morgan Avenue/K-181 from Osborne Street to Delay Street in Downs. Bryant & Bryant Construction Inc., Halstead, Kansas, $694,061.00.

77-18 KA 6079-01: 1/2-inch milling and 1.5-inch overlay from the Oklahoma state line to Arkansas City. APAC-Kansas Inc. Shears Division, Hutchinson, Kansas, $1,397,449.85.
Peace to you, and... don't drive like my brother.

R.P.K.

kphoger

Quote from: route56 on January 24, 2021, 08:11:19 PM
235-87 KA 3232-03: Wichita North Junction Phase 2A: Replace the loop ramp from northbound I-135 to southbound I-235 with a two-lane flyover.

Glory, hallelujah!
Keep right except to pass.  Yes.  You.
Visit scenic Orleans County, NY!
Male pronouns, please.

Quote from: Philip K. DickIf you can control the meaning of words, you can control the people who must use them.

route56

Awarded bids for January have now been posted.

Quote from: J N Winkler on December 21, 2020, 09:29:13 PM
I think the January 2021 letting may set a record for pure signing contracts in a single KDOT letting--I count four signing & delineation (non-freeway) and one sign truss replacement. 

And the same contactor was awarded all four of the non-freeway signage projects. :D
Peace to you, and... don't drive like my brother.

R.P.K.

route56

The February 2021 lettings were paused for 48 hours due to the possibility of rolling blackouts in Topeka. Bids are now scheduled to be read on Friday, February 19, and it appears that the bids submitted prior to the decision to postpone the letting cannot be accepted and the contractors must re-submit their bids.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#265
Approved bids found on KDOT Website 5/13/21
Approved Bids announced 5/18/21

March 2021

All Projects are Federal-Aid unless noted

35-46 KA-6051-01: Pavement marking from I-435 to the Johnson/Wyandotte county line
35-105 KA-6052-01: Pavement marking in Wyandotte County.
Twin Traffic Marking Corporation, $1,015,463.90

69-46 KA-5684-01: Bridge repair of the northbound US 69 bridges over 191st and 179th Street. PCI Roads, LLC, Saint Michael, Minnesota, $846,863.77

10-46 KA-5774-01: Replacement of the eastbound K-10 bridge over Lexington Avenue (ex K-285) in DeSoto. Traffic moving head-to-head on the westbound K-10 bridge. The ramp from eastbound K-10 to Lexington Avenue will remain open, but the ramp from Lexington Avenue to eastbound K-10 will be closed. Detour via westbound K-10 to Edgerton Road. Clarkson Construction Company, $2,693,082.00

169-46 KA-5943-01: PCCP patching, 2-inch milling, and 2-inch overlay on US 169/K-7 from 199th Street to I-35. Idecker Incorporated, $2,795,229.49

31-70 KA-2365-01: Reconstruction of K-31 from the east city limits of Osage City east to the US-75/K-31 junction. (This is a deferred T-WORKS project) Bettis Asphalt & Construction, Inc., Topeka, Kansas, $15,628,203.09

16-75 KA 5720-01: Bridge repair (the plan link consists of a single sheet of traffic control devices, it does not specify the exact location of the project) Bettis, $118,888.99

24-81 KA-3926-01: Bridge replacement on US-24: Bridge #008 (Wildcat Creek Drainage) just north of Riley. Detour via US 77 and K-82. Klaver Construction Company, $412,828.43

50-9 KA-5983-01: 3.5-inch milling and 3-inch overlay on US 50 from K-150 to K-177. APAC-Kansas, Inc., Shears Division, Hutchinson, Kansas, $1,352,341.90

70-21 KA-6067-01: Pavement patching on I-70 from Abilene to Chapman Emery Sapp & Sons, Inc. and subsidiaries, $663,318.50

57-31 KA-5678-01: Repair of the K-57 bridge over Clarks Creek southeast of Junction City Re-let July 2021

45 C-4984-01: Major collector signage replacement on roads south of US 36 and east of K-14 in Jewell County Signs Up LTD DBA Haren's Trees and Critters, Webster City, Iowa,  $72,347.00

25-55 KA-5981-01: 2.5-inch milling, 2.5-inch inlay, and 1.5-inch overlay from the Wichita/Logan county line north ~ 15 miles. Venture Corporation, Great Bend, Kansas, $3,458,059.10

25-97 KA 5982-01: 2.5-inch milling, 2.5-inch inlay, and 1.5-inch overlay from Colby to the Thomas/Rawlins county line. McCormick Excavation & Paving LLC, $2,625,372.02

68-30 KA-5694-01: Repair of the K-68 bridge over the Marais Des Cynges river on the west side of Ottawa. PCI Roads, $1,160,402.00

30 TE-0482-01: Pedestrian improvements near the K-68/Locust Street intersection.

179-39 KA-5155-01: Reconstruction of Jennings Street (K-179) in Anthony from Hayes Street to Evans Street Wildcat Construction Co. Inc. & Subsidiaries, $581,507.32

56-73 KA-3265-02: Replacement of the US-56 bridge over Big Coon Creek Bridge and reconstruction of the roadway northeast to the west city limits of Garfield. Venture, $4,459,106.64

80 C-4969-01: Major collector signage replacement on roads south of US 56 and east of K-14 in Rice County Signs Up, $67,980.00

96-87 KA-5690-01: Bridge repair on the westbound K-96 bridges over Ridge Road and Little Slough Creek northwest of Wichita. PCI Roads, $491,953.05

93 C-4979-01: Major collector signage replacement on roads north of US 50 and west of US 281 in Stafford County, plus NE 70th Street from US 281 east to NE 80th Avenue Century Fence Co., $261,754.69

13 C-4974-01: Major collector signage replacement on roads south of US 160 and west of US 183 in Clark County Signs Up, $62,141.50

13 TE-0477-01: Sidewalk installation on Locust Street from Oak Street to Poplar Street, and Main Street from Locust Street to Ash Street in Minneola APAC-Kansas, $559,923.60

34 C-4981-01: Major collector signage replacement on Road 5 from Road B to the Grant/Haskell county line, Road Q from US 160 to Road 5, and Road V from US 160 to Road 5 in Grant County Signs Up, $25,290.75

35 C-4994-01: Minor collector signage replacement in Gray County Signs Up, $27,740.50

25-47 KA-5156-01: Reconstruction of Main Street (K-25) from C Avenue to Santa Fe Avenue in Lakin. Smoky Hill, LLC, $768,736.65

89 TE-0464-01: Deer Creek Trail Phase 3 in East Topeka Bettis, $2,169,676.63

156-27 KA-6101-01: Chip seal on K-156 from K-140 to I-70 [non-FA] Vance Brothers Inc. and Subsidiary, $504,466.32
Peace to you, and... don't drive like my brother.

R.P.K.

route56

February project listing has been updated with awarded bids announced March 10.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#267
April 2021

Approved Bids announced 5/18/21

Federal-Aid:

35-46 KA 6070-01: 2-inch milling and 2-inch HMA overlay from the I-635 interchange to the Johnson/Wyandotte county line. Superior Bowen Asphalt Company LLC, Kansas City, Missouri, $1,102,830.82

170-70 KA 3918-01: Replace the Marais des Cygnes river bridge east of Reading. K-170 to be closed at the bridge, detour via K-31, US 56, and K-99. A M Cohron & Son Inc., Atlantic, Iowa, $3,525,628.98.

32-105 KA 5682-01: Repair of the Turner Diagonal bridge over the Kansas River. PCI Roads, LLC, Saint Michael, Minnesota, $528,318.81.

169-105 KA 5695-01: Repair of the 7th Street Trafficway bridge over I-70. R A Knapp Construction Inc., Lenexa, Kansas, $722,039.32.

171-11 KA 5776-01: Repair of the K-171 bridges over the Kansas City Southern Railroad and Taylor Creek. Mission Construction Co Inc., St. Paul, Kansas, $768,755.40.

87 N 0674-01: Addition of a right-turn lane on westbound Patriot Avenue at K-15 in Derby. Pearson Construction LLC, Wichita, Kansas, $853,048.70.

50-35 KA 5430-01: Full-depth reconstruction of a one-block section of US 50 between Pine and Maple streets in Cimarron. Smoky Hill LLC, Salina, Kansas, $439,373.25.

86 C 4968-01: Major collector signage replacement - South of K-96 and west of US 83. Martin Outdoor Enterprises Inc., Pittsburg, Kansas, $29,210.00.

30 C 5056-01: Side-of-road stabilization on Virginia Road near Douglas Road in southeastern Franklin County. Killough Construction Inc., Ottawa, Kansas, $259,519.45.

Non-FA:

75-89 KA 5976-01: PCCP patching and 3-inch HMA Overlay on US 75 between Topeka Boulevard and 53rd Street
75-106 KA 5974-01: 1.5-inch Overlay from US 56 in Osage County to Topeka Boulevard in Shawnee County.
Hamm Inc., Perry, Kansas, $6,617,003.59.

24-14 KA 6116-01: Mill and overlay on US 24 in Clay county, excluding  Clay Center. Vance Brothers Inc. And Subsidiary, Kansas City, Missouri, $707,890.45.

106 KA-6140-01: Rumble Strip grinding on US 81 from Concordia to the Nebraska line and K-82 from Wakefield to US 77. Surface Preparation Technologies LLC, New Kingstown, Pennsylvania, $85,043.25.

36-77 KA 6112-01: 2-inch surface recycling and chip seal from Atwood to the Rawlins/Decatur county line. Dustrol Inc., Towanda, Kansas, $1,160,161.16.

254-8 KA 6145-01: Full-depth pavement replacement on the south side of the intersection of K-254 and Shumway Road. APAC-Kansas Inc. Shears Division, Hutchinson, Kansas, $68,760.00

235-87 KA 6003-01: Replacement of the Southbound sign truss at the I-235/Zoo Boulevard interchange. Fulsom Brothers, Inc., Cedar Vale, Kansas, $181,461.45.

106 KA 6138-01: Rumble strip grinding on US 54 and K-254 in Butler county and K-196 in Harvey County. Surface Preparation Technologies LLC, $92,304.74.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#268
The May project lettings mostly consist of maintenance projects, with a few bridge replacements.

May 2021

Approved Bids announced 6/10/21

Federal-Aid:

73-7 KA 5696-01: Milling, concrete overlay, and repair of concrete surfaces on the bridges over the UP Falls City Subdivision and Kestrel Road near Reserve. PCI Roads, LLC, Saint Michael, Minnesota, $839,846.55.

36-22 KA 6009-01: Lighting replacement at the US 36/K-238 interchange near Elwood. Wildcat Construction Co. Inc. & Subsidiaries, Wichita, Kansas, $173,825.00

10-23 KA 5683-01: Repair of the Eastbound K-10 bridge over the Wakarusa River near Eudora. PCI Roads, $1,413,704.02.

435-46 KA 5681-01: Bridge Re-Deck, Seeding, Lighting, and Pavement Marking in the Renner Road bridge over I-435. Clarkson Construction Company, Kansas City, Missouri, $3,432,513.90.

435-46 KA 6071-01: Mill and HMA overlay between Midland Drive and the Kansas River bridge. Ideker Incorporated, Saint Joseph, Missouri, $2,946,893.55

35-46 KA 6074-01: Patching and overlay on I-35 from Lone Elm Road to US 169/K-7. Bettis Asphalt & Construction Inc., Topeka, Kansas, $6,277,433.79.

46 KA 6147-01: Pavement marking on US 69 from 135th to 151st, and I-435 from Metcalf to State Line. Twin Traffic Marking Corporation, Kansas City, Kansas, $723,728.85.

70-89 KA 6073-01: 3.0" overlay on I-70 from MacVicar to the Polk-Quincy Viaduct. Bettis, $1,698,613.16.

70-105 KA 6072-01: Mill and HMA overlay from 110th Street to I-435. Bettis, $1,736,838.48.

177-9 KA 5439-01: Replacement of the bridge over the BNSF Emporia Subdivision north of Matfield Green. The bridge is being replaced to accommodate upgrading the single-track line to double-track, plus accomodating a potential third track. Kings Construction Co. Inc., Oskaloosa, Kansas, $7,337,256.27.

70-32 KA 6066-01: Mill and HMA overlay from 4 miles east of K-211 to the Gove/Trego county line. APAC-Kansas Inc. Shears Division, Hutchinson, Kansas, $6,868,840.41.

70-91 KA 6068-01: Mill and HMA overlay from Edson to the Sherman/Thomas County line
70-97 KA 6069-01: Mill and HMA overlay from the Sherman/Thomas County line to Brewster.
APAC-Kansas, $4,771,497.58

35-30 KA 6010-01: Lighting upgrade at the south I-35/US 59 junction on the south side of Ottawa. Cooper Construction LLC, Emporia, Kansas, $269,839.00.

17 C 4985-01: Minor collector signing upgrade in Comanche County. Signs Up LTD DBA Haren's Trees and Critters, Webster City, Iowa, $115,026.92.

78 C 4977-01: Major collector signing upgrade in Reno County east of K-14 CC & I Engineering Inc./DBA Compass Consultants, Perham, Minnesota, $365,245.68

Federal-Aid, Local Projects:

81 C 4989-01: Replacement of the Rosehill Road bridge over Little Sweede Creek. Ebert Construction Co Inc & Subsidiary, Wamego, Kansas, $385,903.23.

Non-FA:

10-46 KA 5995-01: Replacement of an overhead sign gantry on westbound K-10 east of Renner. Cooper, $97,517.55.

75-89 KA 6006-02: Bridge repair of the northbound US 75 bridge over SW 77th Street. Wildcat, $280,168.90.

106 KA 6155-01: Culvert repair (pipe lining, repairing, and replacement) at various locations in KDOT District 1. Amino Brothers Company Inc., Kansas City, Kansas, $636,488.85.

70-105 KA 4946-01: Culvert repair just west of Turner Diagonal. Comanche Construction Inc., Olathe, Kansas, $256,431.85.

36-101 KA 6159-01: Chip seal on the four-lane section of US 36 in eastern Washington County. Vance Brothers Inc. And Subsidiary, Kansas City, Missouri, $360,630.62.

9-20 KA 6149-01: Mill and HMA overlay on K-9 in Decatur County
9-90 KA 6152-01: Mill and HMA overlay on K-9 in Sheridan County
McCormick Excavation & Paving LLC, Stratton, Colorado, $211,298.40.

25-55 KA 6151-01: Mill and HMA overlay from County Road 160 to Russell Springs. McCormick, $120,977.50.

70-91 KA 6146-01: Mill and HMA overlay from Goodland to Edson. APAC-Kansas, $625,674.55.

27-100 KA 6153-01: Mill and HMA overlay from the Greeley/Wallace county line north 1 mile. McCormick, $179,609.90.

54-49 KA 6167-01: Mill and HMA overlay from Greensburg to the Kiowa/Barber county line. Venture Corporation, Great Bend, Kansas, $459,983.00.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

KDOT hasn't announce awarded bids via press release as they have in the past. I found the Awarded Bids for March, but have not yet seen awarded bids for the April letting.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#270
June 2021

Approved bids announced 6/22/21
Approved bids announced 8/10/21

Federal-Aid

69-48 KA 5792-01: Guardrail improvements on Metcalf Avenue (US 69) near the I-35/I-635 interchange. Cooper Construction LLC, Emporia, $31,477.35.

46 N 658-01: Safe Routes to School improvements along Moonlight Road in Gardner. Megakc Corporation, North Kansas City, Missouri, $480,892.00

52 C 5058-01: Major collector signage upgrades along County Roads 13 and 14 in northwest Leavenworth County. CC & I Engineering Inc./DBA Compass Consultants, Perham, Minnesota, $77,786.53.

18-81 KA 6160-01: Pavement marking on K-18 from K-114 near Ogden to K-113 in Manhattan. Cillessen and Sons Inc., Kechi, $801,831.69.

69-105 KA 5148-01: Reconstruction of 7th Street Trafficway from Homer Avenue to Tenny Avenue, including portions of Central Avenue and Simpson Avenue. Amino Brothers Company Inc., Kansas City, Kansas, $1,846,176.55

635-105 KA 5627-01: Replace deck and rails, paint superstructure, add shear studs, replace expansion joints, replace bearings, abutment repairs, guardrail repair and replace approach slabs on two bridges located at the east I-635/K-5 interchange. Miles Excavating, Inc., Basehor, $5,237,806.66.

635-105 KA 5923-01: Repair the I-635 bridge over the Kansas River. PCI Roads, LLC, Saint Michael, Minnesota, $113,755.20.

135-85 KA 5680-01: Bridge repair on various bridges on I-135 in the Salina area
135-85 KA 6064-01: 3-inch Overlay on I-135 in Saline County.
APAC-Kansas Inc. Shears Division, Hutchinson, $19,033,402.43.

70-26 KA 6011-01: Lighting upgrade on I-70 at K-255 near Victoria (Exit 168) and on US 183 Bypass at Campus Drive in Hays. IES Holding Inc &amp; Subsidiaries, Holdrege, Nebraska, $188,953.00.

70-32 KA 6012-01: Lighting upgrade on I-70 at US 40 near Oakley. (Exit 76) IES, $143,845.00.

70-91 KA 6013-01:  Lighting upgrade on I-70 at the East junction US 24B near Goodland. (Exit 19) IES, $155,453.00.

70-98 KA 6014-01:  Lighting upgrade on I-70 at K-147 near Ogallah. (Exit 135) IES, $151,767.00.

383-74 KA 2372-03: Reconstruction of K-383 from the Prairie Dog Creek Bridge near MP 111 to US 183. Detour via K-60, US 36, and US 183. Venture Corporation, Great Bend, $13,340.00.

10 C 4976-01: Major collector signage upgrade in Chautauqua County west of K-99. CC & I/Compass, $140,947.60

69-19 KA 5149-01: Reconstruction of US 69 and McKay Street in Frontenac. B & B Bridge Company LLC, St. Paul, Kansas, $521,885.00

25 C 4995-01: Minor collector signage upgrade in Elk County Signs Up LTD DBA Haren's Trees and Critters, Webster City, Iowa, $121,581.42

152-54 KA 5147-01: Adding turn lanes at the Market Street/Industrial Boulevard intersection in La Cynge. Killough Construction Inc., Ottawa, $775,762.17

54-8 KA 5799-01: Guardrail installation on US 54 between Rosalia and the Butler/Greenwood county line. Bettis Asphalt &amp; Construction Inc., Topeka, $722,014.84.

18 C 4972-01: Major collector signage upgrade in southern Cowley County. Signs Up, $200,352.42

50-40 KA 5797-01: Guardrail upgrade on US 50 north of the I-135 junction northeast of Newton. Cooper, $36,932.83.

14-78 KA 5798-01: Guardrail upgrade on K-14/K-96 south of South Hutchinson.

Federal-Aid, Local projects

99 C 5054-01: Reconstruction of a short section of Skyline Drive near Allendorph. Hamm, Inc, Perry, $558,228.79

57 C 5046-01: Culvert reconstruction at 290th Street near Elk Road west of Lincolnville Ebert Construction Co Inc & Subsidiary, Wamego, $222,491.08

90 C 4997-01: Bridge replacement on a local road over the North Folk Solomon River in Sheridan County. L & M Contractors, Inc., Great Bend, $574,436.50

Non-FA

106 KA 6161-01: RAP sample millings on various locations in KDOT District 3. Venture, $13,340.00.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

Lettings for May updated with awarded bids announced in a June 10 KDOT release.
Peace to you, and... don't drive like my brother.

R.P.K.

route56

#272
Approved Bids Announced 8/10/2021
Approved Bids Announced 8/30/2021

July 2021

The July lettings include a couple of major projects.

Federal-Aid:

59-23 KA 5794-01: Guardrail replacement on the bridges on US 59 between N 1100 Road and K-10 south of Lawrence. Bettis Asphalt & Construction Inc., Topeka, $220,531.48

24-23 KA 6190-01: Pavement Marking on US 24 from the Jefferson/Douglas County line to K-32, including a 1/2-mile segment of US 40/US 59 south from US 24 at Teepee Junction
24-44 KA 6191-01: Pavement Marking on US 24/59 from the US 24/US 59 junction near Williamstown to the Jefferson/Douglas County line
59-44 KA 6192-01: Pavement Marking on US 59 from the US 24/US 59 junction near Williamstown to Oskaloosa
73-52 KA 6188-01: Pavement Marking on US 73/K-7 from 4th and Metropolitian in Leavenworth north to Millwood Road northwest of Leavenworth.
92-52 KA 6189-01: Pavement Marking on K-92 from 4th and Metropolitian in Leavenworth to the Centennial Bridge
Century Fence Co, Pewaukee, Wisconsin, $625,920.98

46 KA 5496-01: Lighting replacement on I-35 at I-635, 95th Street, and the southbound weight station southwest of Olathe, as well as US 69 at College Boulevard. Gerstner Electric Inc., Fenton, Missouri, $905,529.00

268-70 KA 6194-01: Pavement Marking along the entire length of K-268. Century Fence, $125,637.29

4-89 KA 5795-01: Guardrail upgrades in Shawnee County. Although listed as a project on K-4, much of the bridges are on US 40 east of Topeka, with a couple on US 24 northwest of Topeka, and one on K-4 near the US 24 junction northeast of Topeka. Bettis, $989,838.21

105 KA 5495-01: Lighting upgrade on K-7 at K-32 in Bonner Springs, I-70 at 57th Street, and I-35 between the 18th Street Expressway and Southwest Boulevard. Gerstner, $1,370,562.00

5-105 KA 5796-01: Guardrail upgrades on the "Fairfax Spur" segment of K-5 in Kansas City.

57-31 KA 5678-01: Repair of the Clarks Creek bridge on K-57 southeast of Junction City. Wildcat Construction Co. Inc. & Subsidiaries, Wichita, $263,616.04

177-64 KA 2368-01: Reconstruction of K-177 from K Road to the Morris/Dickinson County Line
177-31 KA 2369-01: Reconstruction of K-177 from the Morris/Dickinson County Line to I-70
Wildcat, $52,307,810.13

55 C 4996-01: Collector road signage upgrade in Logan County. CC & I Engineering Inc. / DBA Compass Consultants, Perham, Minnesota, $304,748.94

84 TE 0483-01: New sidewalk along the west side of Fossil Street in Russell Multicon Inc., Wichita, Kansas, $350,524.86

166-11 KA 1005-02: New US 166/US 400 4-lane freeway from the west US 160/US 400 Junction to K-26. Re-let September 2021

160-63 KA 5424-01: Reconstruction of Main Street in Independence from 10th Street to 8th Street. Bryant & Bryant Construction Inc., Halstead, $1,231,060.00

281-5 KA 3891-01: Replace the bridge over the Blood Creek Drainage northwest of Hoisington. Traffic to be controlled by signals. Venture Corporation, Great Bend, $1,005,086.50

54-8 KA 5605-02: Guardrail upgrades on US 54/US 77/US 400 between Augusta and the East junction with US 400. Bettis, $897,933.25

54-8 KA 5676-01: Repair of a culvert on US 54 east of Rosalia. Snodgrass & Sons Construction Company Inc., Wichita, $264,824.60

96-87 KA 5606-02: Guardrail replacement of K-96 from Hillside Road to Webb Road in Wichita. J & J Contractors, Inc., Iola, $1,550,102.65

87 N 0691-01: Reconstruction of 61st Street in Park City from the Big Ditch to Broadway and a roundabout at 61st and Broadway. Conspec Inc. DBA Kansas Paving, Wichita, Kansas, $3,596,938.64

235-87 KA 5510-02: Guardrail upgrade at the north junction of I-135 and I-235. J & J Contractors, $1,132,631.04

Federal-Aid, Local projects

79 C 4992-01: 79 C 4992-01: Replacement of a Bridge over Dry Creek 4.0 miles south and 0.2 miles east of Republic. Reece Construction Company, Inc., Salina, Kansas, $339,479.215

5 C 4965-01: RCB extension on NW 50th Road and reconstruction of the NW 50th Road/Washington Avenue intersection. L & M Contractors Inc., Great Bend, $603,844.25

Non-FA:

106 KA 6172-01: RAP sample milling at various location in KDOT district 2 Dustrol Inc., Towanda, $15,164.44

106 KA 6210-01: Sidewalk ramp construction in Tonganoxie, Melvern, Holton, Frankfort, Olsburg, Clifton, Sylvan Grove, Lebanon, Sylvan Grove, Franklin/Arma, Caney, Attica, Greensburg, and Coldwater. Bryant & Bryant, $603,726.00

54-8 KA 6186-01: Crack sealing on US 54/US 400 from Andover to Augusta.

50-40 KA 6187-01: Crack sealing on US 50 from I-135 to the Harvey/Marion County line. Snodgrass & Sons Construction Company Inc., Wichita, $264,824.60

54-48 KA 6171-01: Crack Sealing on US 54/US 400/K-14 from Kingman to the east junction with K-14. Pavement Pro's LLC, McPherson, $81,979.90

183-83 KA 6174-01: Crack Sealing on US 183 from La Crosse to the Rush/Ellis county line. R A Knapp, $150,420.30

81-96 KA 6175-01: Crack sealing on US 81 from the Oklahoma State line to Wellington R A Knapp, $206,017.80

254-87 KA 5917-01: Repair damage to pre-stressed beams on Woodlawn Avenue bridge over K-254 near Kechi. PBX Corporation & Subsidiary, Sapulpa, Oklahoma, $28,938.23

106 KA 6181-01: Crack sealing on K-19 from US 50 to the K-19 spur and on the K-19 spur from K-19 to US 56 in Edwards and Pawnee counties. R A Knapp, $194.520.85

106 KA 6193-01: RAP sample milling at various locations in KDOT district 6. Dustrol, $25,090.10
Peace to you, and... don't drive like my brother.

R.P.K.

mvak36

Quote from: route56 on June 19, 2021, 09:15:46 PM
July 2021

The July lettings include a couple of major projects.

166-11 KA 1005-02: New US 166/US 400 4-lane freeway from the west US 160/US 400 Junction to K-26.


That's a good start to their eventual plan (in the distant future) of having a freeway from Overland Park all the way to the Missouri border. Maybe they can nudge Missouri into converting their short segment into a freeway as well to have a free flowing connection to I-44  :poke:.
Counties: Counties visited
Travel Mapping: Summary

route56

The first round of bid awards for June and the remaining bid awards for May were announced on June 22. May and June lettings updated.
Peace to you, and... don't drive like my brother.

R.P.K.



Opinions expressed here on belong solely to the poster and do not represent or reflect the opinions or beliefs of AARoads, its creators and/or associates.