An interesting development for the Thruway rest area reconstruction project:
now state (or toll) money are needed to complete the project. Not a lot, just mere quarter billion:
https://buffalonews.com/news/local/govt-and-politics/new-york-state-thruway-rest-stops-bailout-taxpayers/article_e33d4a6a-d48e-11ed-aeb9-8b215c14e25d.html
It still blows my mind that the larger facilities that were built from scratch in the early 1990s were ripped down at barely 30 years old. I can see the few old facilities from the 50s being replaced, but the ones from the 90s? Complete waste of money.
There is some backstage information, and if that is true - things are very ... Newyorkish.
https://twitter.com/scotvega18/status/1639614250204254208?s=21&t=y732DGKg3Dk5dv5QCjflOQ
https://twitter.com/scotvega18/status/1639614282882064385?s=21&t=fM5R_Rble2S1Y8VKrk8uDA
I'm not sure what the PTC did on the Turnpike for its renovations but nearly all of them were much smaller than the Thruway locations (either they were 1940s buildings or modeled after them). In the case of the Thruway, it sounds like they weren't making them all uniform in size but keeping different size ones, so remodeling might have made some sense.
Thruway did have several different building designs and sizes. Not all of them were best fit, obviously, and they could use a facelift (show me the building which doesn't need one!).
Yet, many people thought those buildings were in reasonable shape. Now a professional hired to do evaluations says that buildings were in reasonable shape - but someone above was hell bent on total rebuild. It could make some sense for a new contractor to start things from scratch, though...
Now, it sounds like new builds are not adequate for the purpose; were deliberately designed in expensive way; and contractor runs out of money and wants state bailout, despite contractually responsible for the scenario.
I, for one, doubt that operational profit is the driving force for the new plaza operator. For one, previous operator terminated operations when contract expired at the end of 2022. Kitchen equipment was removed at areas which were slated to close later, and cold wraps are available now. Not that McD serves great food, but those McDs were still running full steam.
ANd now government bailout - and no services as an alternative, I assume.
Pure speculation, of course, but looks like they made enough campaign donations to ensure they get the contract they wanted - but not (yet) enough to secure bailout...