TX 146 Kemah/Clear Lake Bridge & Freeway Project
Didn't get a great look at this, as I was in a bus and didn't go across the bridge, but the southern approach to the bridge is coming along nicely. The metal beams forming the bridge deck all are in place. No work appears to be done on the SB feeder (assuming there will be one). This will all be completed by early 2023.
TX 36 Widening, Western Brazoria County & Fort Bend County
I was almost completely unaware that this project was so far along. The project to expand TX 36 from 2 to 4 lanes extends from Pleak to West Columbia (for those unfamiliar, this is south-southwest of the Houston metro). I drove the section south of Damon this weekend. TxDOT is twinning the current two lane road, making a divided highway with quite a nice, large median. For the section I drove, concrete was almost completely poured and ready except for the bridge over Varner Creek, which looks way behind schedule at first glance (only piers atm, but lots of work vehicles were in the area, so perhaps TxDOT saved it for last). There will be no bypasses of any towns along the route, and it is supposed to be complete by October of this year, but I would be surprised if it opens any earlier than 2023.
That being said, this is a valuable project that will increase safety and evacuation capacity, as I have argued for a while.