http://www.dot.state.tx.us/insdtdot/orgchart/cmd/cserve/bidtab/01073235.htmBids were opened for the construction of decks over Spur 366 for the expansion of Klyde Warren park. The lowest bid is 101% above the estimate of $47.2 million.
This is surprising, since the deck extension is short, with one section between St. Paul and Akard and then a section on the west side of Akard. Between St. Paul and Akard an event center is planned for the deck. Webber, which is probably the second most competitive bidder in Texas (after Williams Brothers), was 128% over the estimate.
I'm thinking this will throw the park expansion project into turmoil, since the overall cost was estimated around $100 million and this is a 50% increase. It took years to arrange financing for the estimated cost. I'm thinking TxDOT will rebid, and they will probably cut the project in half by postponing the section west of Akard (which is the green area in the depiction).
County: DALLAS Let Date: 01/07/22
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE Seq No: 3235
Time: 0 X Project ID: STP 2022(386)MM
Highway: SS 366 Contract #: 01223235
Length: 0.206 CCSJ: 0196-07-034
Limits:
From: WEST OF AKARD ST Check: $100,000
To: SAINT PAUL ST Misc Cost: $2686811.55
Estimate $47,197,572.82 % Over/Under Company
Bidder 1 $94,966,147.78 +101.21% ARCHER WESTERN CONSTRUCTION, LLC
Bidder 2 $107,624,544.53 +128.03% WEBBER, LLC