Here are the two articles:
Interstate 49 taking shape around Texarkana
Local heads international group aimed at getting corridor built
Unfortunately you have to pay in order to view the articles.
I broke down and spent the $1.95 per article to have them emailed to me. Points of interest to me from first article:
- Nearly 8 mile stretch from Arkansas Boulevard to US 71 is proceeding ahead of schedule and, although scheduled to completed by spring 2013, should be finished and open to traffic within a year.
- Sanderson Lane will have an interchange; Sugar Hill Road will not.
- The new bridges over I-30 serve as a nesting area for cliff swallows; under the Migratory Bird Act, no work on the bridges can be done while the cliff swallows are nesting.
The second article discusses how a Texarkansan heads the I-49 International Coalition and how that group is constantly trying to keep I-49 in the forefront of legislators' minds for whenever more money becomes available. The article mentions $10 billion as amount for Arkansas.
EDIT
One other note from the first article:
- Part of the overall project is replacing the concrete on AR 245 from US 67 to Arkansas Boulevard.