The project to extend NC 540 across southern Wake County to its connection with I-40/Future I-42 is about to get underway; I think it deserves a separate thread.

NCDOT will advertise three design-build contracts, and the first one should go out for proposals next month. The estimated total cost of the three projects is about $1 billion. This is a toll road project to be operated by the NC Turnpike Authority when it is complete.

On April 12 NCDOT is holding a "optional industry event to discuss the projects and the upcoming procurements." There's a news release on this event here:
https://apps.ncdot.gov/newsreleases/details.aspx?r=15003

Strider:

--- Quote from: wdcrft63 on March 27, 2018, 06:05:36 PM ---The project to extend NC 540 across southern Wake County to its connection with I-40/Future I-42 is about to get underway; I think it deserves a separate thread.

NCDOT will advertise three design-build contracts, and the first one should go out for proposals next month. The estimated total cost of the three projects is about $1 billion. This is a toll road project to be operated by the NC Turnpike Authority when it is complete.

On April 12 NCDOT is holding a "optional industry event to discuss the projects and the upcoming procurements." There's a news release on this event here:
https://apps.ncdot.gov/newsreleases/details.aspx?r=15003

--- End quote ---


I hope they leave I-540 section alone after the loop is finished. That road doesn't need to be tolled. (see C-470/E-470/NW Parkway in Denver as the only portion of their beltway that isn't tolled is the C-470 one.)

LM117:

--- Quote from: Strider on April 03, 2018, 10:39:32 AM ---I hope they leave I-540 section alone after the loop is finished. That road doesn't need to be tolled. (see C-470/E-470/NW Parkway in Denver as the only portion of their beltway that isn't tolled is the C-470 one.)

--- End quote ---

IIRC, NCDOT cannot legally toll I-540 as it is now, but they can build new toll lanes if they wanted to, like they’re currently doing on I-77 near Charlotte.

froggie:
^ Technically, NCDOT could apply tolls to I-540 at the Neuse River Bridge, with the caveat that any toll revenue could only be used to maintain/improve that segment of I-540 (US 401 to Buffaloe Rd, include the river bridge).  This is because current Federal law allows jurisdictions to apply tolls to Interstate bridges and tunnels as long as the revenue is only used to maintain/improve that bridge or tunnel location and immediately adjacent segments of the Interstate in question.  This is how VDOT was able to reinstate tolls on the I-264 Downtown Tunnel between Portsmouth and Norfolk, VA.

Strider:

--- Quote from: froggie on April 03, 2018, 01:10:34 PM ---^ Technically, NCDOT could apply tolls to I-540 at the Neuse River Bridge, with the caveat that any toll revenue could only be used to maintain/improve that segment of I-540 (US 401 to Buffaloe Rd, include the river bridge).  This is because current Federal law allows jurisdictions to apply tolls to Interstate bridges and tunnels as long as the revenue is only used to maintain/improve that bridge or tunnel location and immediately adjacent segments of the Interstate in question.  This is how VDOT was able to reinstate tolls on the I-264 Downtown Tunnel between Portsmouth and Norfolk, VA.

--- End quote ---


They could, but I don't think they're going to do it. Building a toll lane(s)? I could see that.

Navigation