Work continues in the widening of Interstate 40 between Conway and the I-430 interchange. Weather permitting next week, work on this project will begin. Night lane closures to set barrier wall followed by two lanes of open traffic while third lane is added in median.

See news release published today: http://www.arkansashighways.com/news/2014/NR%2014-012.pdf (http://www.arkansashighways.com/news/2014/NR%2014-012.pdf)

News release announcing bid approval for this project: http://www.arkansashighways.com/news/2013/Bid%20Opening/September/FAULKNER%20&%20PULASKI%20COUNTIES.pdf (http://www.arkansashighways.com/news/2013/Bid%20Opening/September/FAULKNER%20&%20PULASKI%20COUNTIES.pdf)
Title: Re: Arkansas Work Zone - I-40 from Palarm Creek to SH 365 (012145)
Post by: msunat97 on February 03, 2014, 12:32:04 PM
AHTD...what's the timing of completion of the Conway section of the project? 
Title: Re: Arkansas Work Zone - I-40 from Palarm Creek to SH 365 (012145)
Post by: AHTD on February 03, 2014, 12:34:56 PM
Everything under construction now - including this new project (012145) should be completed by the end of summer 2014.
Title: Re: Arkansas Work Zone - I-40 from Palarm Creek to SH 365 (012145)
Post by: AHTD on February 03, 2014, 04:27:16 PM
This work zone now appears on our new travel and construction information web site: www.idrivearkansas.com (http://www.idrivearkansas.com)

Title: Re: Arkansas Work Zone - I-40 from Palarm Creek to SH 365 (012145)
Post by: msunat97 on February 04, 2014, 01:03:46 PM
Thanks.  There was an article from last year that stated the Conway section would be done early in 2014.  I appreciate the update.