AHTD opened a 3rd lane on I-40 WB from the I-430 interchange to the Morgan / Maumelle exit. This is a new inside lane as part of the I-40 widening project. That should he the traffic flow heading west in the evening rush.
Quote from: msunat97 on November 11, 2015, 09:45:04 AM
AHTD opened a 3rd lane on I-40 WB from the I-430 interchange to the Morgan / Maumelle exit. This is a new inside lane as part of the I-40 widening project. That should he the traffic flow heading west in the evening rush.
EB is a clusterf*ck when you get to 430 with the ramps under construction.
Cluster is an understatement. We'll have to patient for now. It's too dark when I leave work to see any real progress on my home each night.
The I-430 exit from I-40 EB is now open with 2 lanes. The I-430 NB to I-40 WB has the bridge deck poured. The rebar is going up for the barrier. Slowly making progress.
The new lane of the I-430NB to I-40WB is slowly getting ready. The barrier wall is in place. The approach guard rail is in place. Needs paint & the temporary barrier removed.
The new lane of the I-430NB to I-40WB is open to traffic. They need to paint the stripes & remove the orange barrels to open. The new right hand merge lane is ready. It has barrels in it now to keep it closed.
The I-430NB exit to I-40WB is now open with 2 lanes. Looks like the new interchange is done minus some touchup & misc work