I notice that there's a northern bypass of Mobile being constructed along AL-158; any updates on the plans or progress of this highway? Looks like a good alternate route around Mobile instead of US-98 when it's completed.
Not sure of Alabama's procedures in similar situations, but I would not be surprised if US-98 is relocated onto AL-158 once it is completed.
https://www.dot.state.al.us/projects/swregion/SR158ProjectInfo.html
https://www.al.com/live/2012/03/road_to_nowhere_us_98_project.html
Quote from: cockroachking on April 10, 2022, 03:44:44 PM
Not sure of Alabama's procedures in similar situations, but I would not be surprised if US-98 is relocated onto AL-158 once it is completed.
The construction plans for the eastbound lanes base and pave from Mississippi to Glenwood Road shows US-98 signed alongside SR-158 on the new alignment. This means that US-98 will be moved onto the entire SR-158 corridor once all the construction needed to carry at least 2 lanes of traffic between Mississippi and Schillinger Road is completed. The westbound lanes will be base, pave and bridged at a later date when more funding becomes available.
Somebody can and probably will correct me but I assume US-98 will be rerouted along the whole AL-158 route, run concurrently with US-43 then split off and run concurrently with US-90 and rejoin its original alignment on the east end of the Bankhead Tunnel at Government Street.
Much like ALDOT did with US-431 in Anniston.
^ That's not entirely what ALDOT did with 431. They wound up putting 431 concurrent with 20, not 78. By that logic, they would have 98 run down 65 and 165.