Author Topic: Corridor H  (Read 360737 times)

hbelkins

  • *
  • *
  • Offline Offline

  • Posts: 14164
  • It is well, it is well, with my soul.

  • Age: 58
  • Location: Kentucky
  • Last Login: March 27, 2020, 04:15:50 PM
    • Millennium Highway
Re: Corridor H
« Reply #1150 on: January 17, 2020, 11:16:36 AM »

What's the status of WV's construction from the current end of the four-lane eastward toward the state line? Be nice to eliminate that 25 mph speed trap in downtown Wardensville.

I saw something in some news coverage about the Corridor Q (US 460) construction that indicated portions of that route between the state line and Grundy would be built as an improved two-lane with truck lanes on the grades (a surface super-2). Wonder if that couldn't become an option for the Virginia portion of Corridor H?
Logged

tjcreasy

  • *
  • Offline Offline

  • Posts: 44
  • Location: Richmond
  • Last Login: Today at 12:44:20 AM
Re: Corridor H
« Reply #1151 on: January 17, 2020, 03:01:50 PM »

Guys letís just be honest. Thereís no way in h*** any county/city in VA would want to move to WV. You can throw corridor H on the same pile as I-73, I-74, and I-87 none of these will be built within the next 20-30 years. Each route will start as soon as you cross the state line. Each State should have had a cooperative agreement with Virginia before their respective sections were started.

The only new interstate (or Appalachian Development Highway) youíll see in VA within the next 10 years is I-785.
« Last Edit: January 17, 2020, 05:40:49 PM by tjcreasy »
Logged

sprjus4

  • *
  • Online Online

  • Posts: 3682
  • Location: Hampton Roads, VA
  • Last Login: Today at 08:50:31 PM
Re: Corridor H
« Reply #1152 on: January 17, 2020, 03:58:51 PM »

Each route will start as soon as you cross the state line. Each State should have a cooperative agreement with Virginia before their respective sections were started
North Carolina has already said they will not be upgrading US-220 to interstate standards north of NC-68 until Virginia begins their portion near Martinsville, such as the Martinsville Southern Connector project extending the US-220 freeway to the state line.

NC-68 will likely be the northern terminus of I-73 for quite awhile.

Likewise, they will not construct I-73 south of the Rockingham Bypass until South Carolina begins their portion. The under construction Rockingham Bypass is likely the last I-73 segment to be completed for quite awhile as it will finish the interstate throughout the state with the exception of those connecting pieces mentioned above.

As for I-87, the state does plan to complete the interstate to the state line, potentially beginning around 2027. What Virginia does with their segment... who knows. The 12 mile US-17 segment in Virginia is currently under study and is one of the candidate projects for the 2045 LRTP in Hampton Roads... but thatís about it. Until the segment between the Elizabeth City Bypass and the state line is built, there will probably be nothing done in Virginia.
« Last Edit: January 17, 2020, 04:04:02 PM by sprjus4 »
Logged

tjcreasy

  • *
  • Offline Offline

  • Posts: 44
  • Location: Richmond
  • Last Login: Today at 12:44:20 AM
Re: Corridor H
« Reply #1153 on: January 17, 2020, 05:40:06 PM »

Yeah thatís the point of my post @sprjus4.
Logged

sprjus4

  • *
  • Online Online

  • Posts: 3682
  • Location: Hampton Roads, VA
  • Last Login: Today at 08:50:31 PM
Re: Corridor H
« Reply #1154 on: January 17, 2020, 05:44:34 PM »

Yeah thatís the point of my post @sprjus4.
My post was more geared at the fact I-73 won't be extended all the way to the Virginia state line until we build our part.
Logged

tjcreasy

  • *
  • Offline Offline

  • Posts: 44
  • Location: Richmond
  • Last Login: Today at 12:44:20 AM
Re: Corridor H
« Reply #1155 on: January 17, 2020, 06:01:17 PM »

I get your point. To me that remaining 20 miles already has interchanges at every major intersection and zero stop lights at the remaining at-grade intersections. Many sections only require widened shoulders to meet interstate standards. Itís smooth sailing from the NC State Line all the way to Rockingham. That limited access section will be more than adequate for the next 30+ years.
Logged

sprjus4

  • *
  • Online Online

  • Posts: 3682
  • Location: Hampton Roads, VA
  • Last Login: Today at 08:50:31 PM
Re: Corridor H
« Reply #1156 on: January 17, 2020, 06:07:16 PM »

I get your point. To me that remaining 20 miles already has interchanges at every major intersection and zero stop lights at the remaining at-grade intersections. Many sections only require widened shoulders to meet interstate standards. Itís smooth sailing from the NC State Line all the way to Rockingham. That limited access section will be more than adequate for the next 30+ years.
Once I-73 is constructed in Virginia (if ever) and North Carolina upgrades that segment, work will likely involve replacing most if not all of the bridges, as they're all 60s design, old, substandard, structurally deficient and have inadequate vertical clearances, along with expanding the interchanges to meet modern design standards. The few at-grade access points will be closed and frontage roads constructed to provide access, the shoulders widened to 10 feet, and the speed limit increased to 70 mph.
Logged

Strider

  • *
  • Offline Offline

  • Posts: 689
  • Location: Greensboro, NC
  • Last Login: March 27, 2020, 08:21:39 PM
Re: Corridor H
« Reply #1157 on: January 19, 2020, 11:28:12 PM »

I get your point. To me that remaining 20 miles already has interchanges at every major intersection and zero stop lights at the remaining at-grade intersections. Many sections only require widened shoulders to meet interstate standards. Itís smooth sailing from the NC State Line all the way to Rockingham. That limited access section will be more than adequate for the next 30+ years.
Once I-73 is constructed in Virginia (if ever) and North Carolina upgrades that segment, work will likely involve replacing most if not all of the bridges, as they're all 60s design, old, substandard, structurally deficient and have inadequate vertical clearances, along with expanding the interchanges to meet modern design standards. The few at-grade access points will be closed and frontage roads constructed to provide access, the shoulders widened to 10 feet, and the speed limit increased to 70 mph.


To add to that, North Carolina is preparing for the upgrade of US 220 to interstate standards. They are currently widening the northbound US 220 lanes across the train tracks to include shoulders near the northern end of Business 220 interchange (the southbound one was already finished). They also have two bridges to be replaced within the next 5 years: the NC 135/US 311 interchange and NC 770 interchange.

Since VA's CTB approved the route for MSC, it is going to get built within next 10-20 years. I-73 will be extended to the state line area eventually.

Back to Corridor H, what is the update on it?
Logged

seicer

  • *
  • Offline Offline

  • Posts: 1394
  • Last Login: Today at 08:33:04 AM
Re: Corridor H
« Reply #1158 on: January 20, 2020, 06:36:46 AM »

What update would there be? It's not like West Virginia is going to annex in some counties in West Virginia, or that Virginia is going to build their section in the near future.
Logged

seicer

  • *
  • Offline Offline

  • Posts: 1394
  • Last Login: Today at 08:33:04 AM
Re: Corridor H
« Reply #1159 on: January 20, 2020, 09:04:54 AM »

I can't wait for Corridor H news to populate this thread again.
Logged

Mapmikey

  • *
  • Offline Offline

  • Posts: 2813
  • Co-curator with Froggie of www.vahighways.com

  • Age: 50
  • Last Login: Today at 03:16:21 PM
    • Co-curator Virginia Highways Project
Re: Corridor H
« Reply #1160 on: January 20, 2020, 09:49:01 AM »

Latest info I can find...

Public comment was held in summer 2018.  The materials with this had a timeline that included expecting a court ruling in 2020, ROW in 2025 and construction start in 2027
https://transportation.wv.gov/highways/engineering/comment/closed/CorridorH-WardensvilletoVaLine/Pages/default.aspx

A document dated August 20, 2019 shows the section as undergoing additional environmental review

Sen Capito and another Congressman were working to put forth legislation that would result in WV getting more Appalachian Corridor Funding - Oct 30, 2019 article.  I have no idea if this got anywhere.
Logged

hbelkins

  • *
  • *
  • Offline Offline

  • Posts: 14164
  • It is well, it is well, with my soul.

  • Age: 58
  • Location: Kentucky
  • Last Login: March 27, 2020, 04:15:50 PM
    • Millennium Highway
Re: Corridor H
« Reply #1161 on: January 20, 2020, 04:33:51 PM »


Sen Capito and another Congressman were working to put forth legislation that would result in WV getting more Appalachian Corridor Funding - Oct 30, 2019 article.  I have no idea if this got anywhere.

I thought that the concept of dedicated APD money is gone, and it all goes into a general pot of federal highway money. If there was dedicated APD money, Virginia would have no excuse to not build its portion.

Interesting observation from that story.

"A segment of approximately 66 miles from Davis to Wardensville in Hardy County is also open to traffic."

That certainly does not feel like a 66-mile-long highway.  The distance seems much shorter.
Logged

seicer

  • *
  • Offline Offline

  • Posts: 1394
  • Last Login: Today at 08:33:04 AM
Re: Corridor H
« Reply #1162 on: January 20, 2020, 05:28:56 PM »

Yep, measures out to around 66 miles. It sure feels shorter but I think that's because you can now go 65 MPH (or let's face it, 75 MPH) instead of 20-55 MPH.

In comparison, the Weston to Kerens segment is 40 miles but it feels much longer!
Logged

Alps

  • Everybody Obeys the Octagon
  • *
  • *
  • Offline Offline

  • Posts: 13166
  • Elimitante the truck trarffic,

  • Age: 37
  • Location: New Jersey
  • Last Login: Today at 04:40:17 PM
    • Alps' Roads
Re: Corridor H
« Reply #1163 on: January 21, 2020, 08:25:00 AM »

Topic locked until people can read the title properly.

Topic unlocked. CORRIDOR H DISCUSSION ONLY.
« Last Edit: January 22, 2020, 12:22:19 AM by Alps »
Logged

mvak36

  • *
  • Offline Offline

  • Posts: 810
  • Super Bowl Champs!!!!

  • Last Login: Today at 12:24:29 PM
Re: Corridor H
« Reply #1164 on: January 22, 2020, 09:31:24 AM »


Sen Capito and another Congressman were working to put forth legislation that would result in WV getting more Appalachian Corridor Funding - Oct 30, 2019 article.  I have no idea if this got anywhere.

I found the bills that this article is talking about: Senate and House

It doesn't look like much progress on them since they've been filed.
Logged