I-80/I-99 West Interchange

Started by qguy, June 16, 2018, 10:04:57 AM

Previous topic - Next topic

MASTERNC

Quote from: webny99 on March 14, 2025, 08:14:59 PM
Quote from: 74/171FAN on March 14, 2025, 03:31:47 PMPennDOT - District 2 News: PennDOT Announces Dates for I-80 Bridge Demolition


So half of the I-80 EB overpass of PA 26 will be demolished, requiring a closure of PA 26, but nothing is mentioned about the impact to I-80 EB itself. Will two lanes somehow be maintained during demolition?

Article says half the bridge will be demolished, so I imagine they would cross one lane over to the other side and run the other across the remaining half of the bridge. This seems to the MO for reconstruction projects on I-80 now


74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

Beltway

All 11 major contracts for the I-80/I-99 high-speed interchange project in Centre County, PA are currently under construction.

Active Construction Scope
+ The main interchange contract includes:
+ 10 bridges
+ 4 retaining walls
+ 5 box culverts
+ 7 sign structures
+ 3 changeable message boards
+ New and rebuilt roadways and ramps
+ ITS devices, highway lighting, and stream improvements
+ Hauling operations began July 14, 2025, and will continue into 2026
+ The Jacksonville Road Betterment and Local Access Interchange phases are also active or completed

Timeline
+ Construction is expected to span six seasons, with full completion by 2030
+ The project is funded in part by $170 million from the Bipartisan Infrastructure Law, out of a total $259 million budget

https://www.pa.gov/agencies/penndot/projects-near-you/district-2-projects/bellefonte-interchange-projects
Baloney is a reserved word on the Internet
    (Robert Coté, 2002)

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

webny99

Quote from: 74/171FAN on November 20, 2025, 10:30:12 AMPennDOT - District 2 News: Traffic Congestion Likely at Bellefonte Interchange Friday (not directly related to the current project)

Staying on PA 26 and entering I-80 at Exit 163 is a far better option during backups.

A pilot vehicle is an interesting concept - it could create longer gaps, but also means traffic behind the pilot will take longer to clear.

74/171FAN

Quote from: webny99 on November 20, 2025, 03:09:31 PM
Quote from: 74/171FAN on November 20, 2025, 10:30:12 AMPennDOT - District 2 News: Traffic Congestion Likely at Bellefonte Interchange Friday (not directly related to the current project)

Staying on PA 26 and entering I-80 at Exit 163 is a far better option during backups.

A pilot vehicle is an interesting concept - it could create longer gaps, but also means traffic behind the pilot will take longer to clear.

I probably would just take PA 64 and enter I-80 at Exit 173.
I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.

Travel Mapping: https://travelmapping.net/user/?units=miles&u=markkos1992
Mob-Rule:  https://mob-rule.com/user/markkos1992

74/171FAN

PennDOT - District 2 News: PennDOT Updates Drivers on I-80 Construction in Centre County

QuoteClearfield, PA – The Pennsylvania Department of Transportation (PennDOT) updated drivers on a pair of construction projects impacting Interstate 80 (I-80) in Centre County; one to enhance traffic safety by providing a direct connection between I-80 and Interstate 99 (I-99) and the other to improve the ride quality and extend the service life of nearly 12 miles of road in Boggs and Snow Shoe townships.

The contractor for the High-Speed Interchange project between I-80 and I-99 will implement lane closures along I-80 eastbound and westbound starting Tuesday, July 28. These lane closures are expected to continue through Friday, July 31, while the contractor prepares the next phase of traffic control on I-80 eastbound.

Starting on Saturday, August 1, the contractor will maintain two lanes of traffic in each direction through the work zone for the high-speed interchange project. Drivers in the left (passing) lane of I-80 eastbound will use a crossover lane at mile marker 159.2 to travel across the median onto I-80 westbound. Concrete barriers will separate eastbound and westbound traffic while eastbound traffic continues in the westbound passing lane to another crossover lane at mile marker 162.5. Eastbound traffic will use that crossover lane to travel back across the median onto I-80 eastbound.

The current traffic pattern on I-80 westbound, where the contractor is maintaining two lanes of traffic by keeping the right (travel) lane open and shifting traffic onto the shoulder, will remain the same. PennDOT anticipates this pattern remaining in place until the fall of 2027.

Also on Tuesday, July 28, the contractor for PennDOT's Interstate preservation project impacting I-80 between mile markers 147 and 159 in Boggs and Snow Shoe townships plans to begin milling and paving operations, shoulder backup, and guide rail installation on the westbound side. The contractor will close the travel lane between mile markers 157 and 154 resulting in traffic being reduced to a single lane in the westbound direction through the preservation project work zone. PennDOT expects this lane closure to remain in place until early September.

All construction schedules are subject to change due to weather or other unforeseen circumstances.

The high-speed interchange project includes building the interchange, ten bridges, four retaining walls, five box culverts, seven sign structures, and three changeable message boards. It also includes constructing new and rebuilding existing roadways and ramps, drainage improvements, installing Intelligent Transportation System (ITS) devices, guide rail and highway lighting, pavement marking, stream improvements, and miscellaneous construction. Work will continue through the next five construction seasons, ending in 2030. Trumbull Corporation of Pittsburgh, PA, is the contractor on the $259 million contract.

The preservation project near Milesburg includes milling, paving, preservation work on four bridges, installation of various ITS devices, guide rail upgrades, line painting, and miscellaneous construction. Glenn O. Hawbaker, Inc., of State College, PA, is the contractor on the $13.5 million project. PennDOT anticipates work for this construction season ending in November and continuing into the 2027 construction season.

Travelers can check conditions on major roads by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,200 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional X alerts.

Find PennDOT's planned and active construction projects at www.pa.gov/DOTprojects. Subscribe to PennDOT news and find transportation results in Cameron, Centre, Clearfield, Clinton, Elk, Juniata, McKean, Mifflin, and Potter counties at www.pa.gov/DOTdistrict2. 

Find PennDOT news on X, Facebook, Instagram and LinkedIn.

MEDIA CONTACT: Timothy Nebgen, tnebgen@pa.gov or 814-765-0598

Steve Harmic, sharmic@pa.gov or 814-496-6189
I am now a PennDOT employee.  My opinions/views do not necessarily reflect the opinions/views of PennDOT.