kphoger

Quote from: edwaleni on March 23, 2025, 02:52:55 PMThat particular HV line runs from the Grand Tower Power Plant on the Mississippi River to a substation south of West Frankfort. Ameren is only upgrading the line from West Frankfort to the Carbondale North Substation by the airport.

Here's a good view from Freeman Spur Blacktop:

before / after

He Is Already Here! Let's Go, Flamingo!
Dost thou understand the graveness of the circumstances?
Deut 23:13
Male pronouns, please.

Quote from: PKDIf you can control the meaning of words, you can control the people who must use them.


Revive 755

List of projects for the August 1, 2025 Letting is up
  • Item 1X is a review and inspection for reconstructing IL 8/IL 116 interchange with IL 29 in East Peoria and replacing the adjacent bridge over the railyard.
  • Item 2 is the I-39 reconstruction in Rockford from east of Mulford Road to north of Harrison Street.
  • Item 11 is an intersection improvement for IL 58/Golf Road at Barrington Road in Hoffman Estates.
  • Item 12 is another I-80 reconstruction contract around Joliet.  This one is from west of Wheeler Avenue to the Des Plaines River.
  • Item 16 and 17 are trombone mast arm replacement contracts for various locations in Cook County.
  • Item 21 is a building demolition contract around the Old Harlem Avenue/65th Street intersection.
  • Item 29 is improvements for the EB IL 6 ramps at IL 40, including a new permanent traffic signal.
  • Item 48 is improvements for the IL 157 intersection with IL 162.
  • Item 51, already deleted:  "Bridge replacement, pavement reconstruction, ADA and APS improvements, new intersection and traffic signal installation, upgrading drainage system and signage upgrades on IL 203 from 0.1 miles north of IL 3 Connector to 0.1 miles south of IL 3 Connector in Madison."
  • Item 82:  "Reconstruction, widening and resurfacing Fifth Street from I-55 to Lincoln Parkway in Lincoln"
  • Item 83 is extension of MacArthur Boulevard from the current southern end south of I-72 to Woodside Road.
  • Item 87:  "Railroad Separation Structure Replacement at WCL Railroad over I-80 (SN 032-9906) and Bridge Repair at Wabena Rd. over I-80 (SN 032-0065 in Kendall and Grundy Counties."
  • Item 90:  "Signal modifications, railroad interconnects and fiber optic installation on IL 37 from IL 13 to Boyton Street in Marion."

ilpt4u

Item 90: Marion needs Fiber ran down IL 13 more than IL 37 for stoplight syncing, tho useful also on 37

The difference it made in Carbondale a few years ago when IDOT ran fiber for the stoplights is night and day. Can usually get across town with only 1 or 2 red lights. Sometimes can clear with getting 0 red lights, even during the day

Rick Powell

Quote from: Revive 755 on June 27, 2025, 10:03:59 PM
  • Item 87:  "Railroad Separation Structure Replacement at WCL Railroad over I-80 (SN 032-9906) and Bridge Repair at Wabena Rd. over I-80 (SN 032-0065 in Kendall and Grundy Counties."
A long-planned project where the replacement railroad bridge was designed years ago but never constructed, and will fit in nicely with the concurrent add-lanes project on I-80 from Minooka to the east.

ChiMilNet

Quote from: Revive 755 on June 27, 2025, 10:03:59 PM
  • Item 16 and 17 are trombone mast arm replacement contracts for various locations in Cook County.
Sad to progressively see these go. Really, a relic of a previous era on Illinois roadways, and something that always made them look more unique. I get that they are aging and need to be replaced with more modern structures that meet current standards but still sad to see them go.

hobsini2

Quote from: ChiMilNet on June 29, 2025, 11:58:28 AM
Quote from: Revive 755 on June 27, 2025, 10:03:59 PM
  • Item 16 and 17 are trombone mast arm replacement contracts for various locations in Cook County.
Sad to progressively see these go. Really, a relic of a previous era on Illinois roadways, and something that always made them look more unique. I get that they are aging and need to be replaced with more modern structures that meet current standards but still sad to see them go.
They have just completed the Washington St Bridge work in Downtown Naperville. While they were doing that, the intersection of Washington and Chicago had the temp wire signals up. To my shock, they did not replace one of the truss masts (SW corner).
I knew it. I'm surrounded by assholes. Keep firing, assholes! - Dark Helmet (Spaceballs)

Revive 755

List of projects for the September 19, 2025 Letting is up.
  • Item 1:  "This project involves the partial modernization of thirty-six (36) intersection to include Accessible Pedestrian Pushbuttons (APS) and/or Leading Pedestrian Interval (LPI) timing updates. Thirty-six (36) intersections located in the following District 1 counties: Cook, McHenry, Lake, Kane, and Dupage."
  • Item 1X is another review and inspection for the IL 8/IL 116 interchange reconstruction with IL 29 and US 24 in East Peoria.
  • Item 13 is an advance tree removal contract for IL 22 between Quentin Road and IL 83.
  • Item 16 is an advance tree removal contract for IL 31 from Crystal Lake to McHenry.
  • Item 18 is replacing temporary span wire signals with permanent signals at various locations in Cook, DuPage and Will Counties.
  • Item 28 (already deleted) would have been reconstruction and signalization of the US 20/IL 73 intersection.
  • Item 32 is an advance tree removal contract for the I-74/IL 5 interchange.
  • Item 33 is another advertisement for the WCL Railroad overpass replacement on I-80 near Minooka.
  • Item 49:  "Installing helical ground anchors at SN 054-7102 carrying I-55 over a drainage ditch 0.4 miles north of IL 10 near Lincoln."
  • Item 58 is replacing bridges on I-57 at the US 45 interchange near Neoga and at the nearby railroad.
  • Item 61 is bridge replacement on I-57 at Green Creek in Effingham County.
  • Item 65:  "Installation of a median crossover on I-70 approximately 0.4 miles west of the IL 128 interchange."
  • Item 66 is a relisting for the IL 157/IL 162 intersection project.
  • Item 67 is a reposting for IL 3 at the intersections with Pierce Lane and Delmar Avenue in Godfrey.
  • Item 69 is a reposting for IL 203 around the IL 3 Connector in Madison County.
  • Item 77:  "Convert the intersecton of Wolf's Crossing Road and Douglas Road to a roundabout."
  • Item 90:  "Remove and replace traffic signals and pedestrian accommodations along Desplaines River Road and Balmoral Avenue in Rosemont."
  • Item 91 appears to be for widening Randall Road in Kane County at IL 72.
  • Item 97 appears to be a rebid for I-80 west of the Des Palines River Bridge.

kphoger

Quote from: Revive 755 on August 15, 2025, 10:20:22 PMItem 61 is bridge replacement on I-57 at Green Creek in Effingham County.

That's means I-57's bridge(s) over the river named Green Creek, right?  Not a bridge over I-57 near the community named Green Creek nearby (N 1675 or E 1900)?

He Is Already Here! Let's Go, Flamingo!
Dost thou understand the graveness of the circumstances?
Deut 23:13
Male pronouns, please.

Quote from: PKDIf you can control the meaning of words, you can control the people who must use them.

Revive 755

^ Looks like it is the northbound bridge over the creek that passes between the northbound and southbound rest area a little north of I-70.

Revive 755

List of projects for the November 7, 2025 Letting is up.
  • Item 1X (review and inspection only) is for reconstructing the I-57 interchange with IL 116.
  • Item 3 is for redoing the intersection of IL 171 with 95th Street.  The pay item listing suggests it is also getting a signal installed.
  • Item 6 is intersection improvements along IL 50 with a new signal at Dralle Road.
  • Item 7 is for replacing the Devon Avenue overpass across I-94.
  • Item 8 is for bridge improvements on Caton Farm Road over I-55.
  • Item 9 is for replacing the Keeler Street bridge over I-290.
  • Item 10 is another building demolition contract for I-80 in Joliet.
  • Item 14 is a various location sign replacement contract in the Chicago IDOT District
  • Item 26 is an advance fabrication contract for the US 20 Kishwaukee River Bridge, with a listed completion date of July 17, 2028.
  • Item 46 is for tree and vegetation removal along I-55 from 11th Street (just east of the southern/western I-72 interchange to the Stevenson Drive interchange.  Can't tell if it is just a general maintenance type contract or in advance of some reconstruction contract.
  • Item 47 is tree removal along US 67 near the Illinois River bridge.
  • Item 52 appears to be removing the old railroad bridge over I-55 just south of the Stevenson Driver interchange in Springfield.
  • Item 64 is another readvertisement for the IL 157/IL 162 intersection.
  • Item 65 is another readvertisement (fifth time on a letting) for signal work along IL 159 in Fairview Heights.

ET21

    Quote from: Revive 755 on October 03, 2025, 10:47:57 PMList of
    • Item 3 is for redoing the intersection of IL 171 with 95th Street.  The pay item listing suggests it is also getting a signal installed.
    [/li][/list]


    Wonder if that's to cut down on speeders as well in that section. It is due for an upgrade, doing a left from WB 95th to SB 171 is a bit hairy.
    The local weatherman, trust me I can be 99.9% right!
    "Show where you're going, without forgetting where you're from"

    Clinched:
    CA: I-105
    IL: I-80, I-88, I-94, I-180, I-190, I-290, I-294, I-355, IL-390, IL-394
    IN: I-80, I-94
    SD: I-190
    WI: I-90, I-94
    MI: I-94, I-196
    MN: I-90