I know this is barely related and connected to the Grand Parkway, but how's the work off of SH 146 from League City Parkway to Red Bluff Road?
Progress is good as of my last visit in July. The bridge section is the main focus at this time. The main bridge over the channel is mostly complete. The long elevated approaches on the north and south sides have sections that are mostly complete and sections with mostly piers.
North of NASA 1, progress is slower. Traffic was still on the original pavement. Work on the southbound frontage road and main lanes was the main focus.
In a related development, TxDOT opened bids earlier this month to update SH 146 north to SH 225 to 3x3. This involves adding the third lane in each direction where the existing facility lacks the third lane.
County: HARRIS Let Date: 08/05/21
Type: RECONSTRUCT AND WIDEN FREEWAY FACILITY Seq No: 3201
Time: 1229 WORKING DAYS Project ID: C 389-5-87
Highway: SH 146 Contract #: 08213201
Length: 11.521 CCSJ: 0389-05-087
Limits:
From: S. OF SPENCER HWY Check: $100,000
To: S. OF RED BLUFF Misc Cost:
Estimate $123,933,207.35 % Over/Under Company
Bidder 1 $110,766,237.66 -10.62% WILLIAMS BROTHERS CONSTRUCTION CO., INC.