Author Topic: MODOT Contract Lettings  (Read 6014 times)

mvak36

  • *
  • Offline Offline

  • Posts: 627
  • 2016 WS champs!!!!

  • Last Login: October 17, 2018, 10:07:50 PM
Re: MODOT Contract Lettings
« Reply #50 on: August 10, 2018, 01:14:57 PM »

If anyone is traveling in the Independence area for the next month, you might want to avoid the I-70/I-470/MO291 interchange.

https://www.kansascity.com/news/local/article216370225.html
Logged
Counties: Counties visited
Travel Mapping: Summary

mvak36

  • *
  • Offline Offline

  • Posts: 627
  • 2016 WS champs!!!!

  • Last Login: October 17, 2018, 10:07:50 PM
Re: MODOT Contract Lettings
« Reply #51 on: August 10, 2018, 01:22:28 PM »

September 21, 2018 Letting: Bid Results. Bid Award Winners.

Notable Projects:
Job J1P3010 Route 148 NODAWAY County. Resurface and add shoulders from Iowa State line to US 71 near Maryville, the total length of improvement being 14.149 miles.
Job J2M0276 Route 63 ADAIR, MACON County. Pavement improvements from 1.2 miles south of Route KK near Kirksville to 0.5 miles north of Route DD near Macon, the total length of improvement being 20.917 miles.
Job J4S3284 Route 69 CLAY, PLATTE County. Grading, drainage, bridge and paving at Frontier Road in Northmoor, the total length of improvement being 0.094 miles.
Job J4P3295C Route 45 PLATTE County. Pavement marking from Route 45 at Riss Lake Dr. and Klamm Road, the total length of improvement being 0.546 miles.
Job J5P3212 Route 21, 32 WASHINGTON County. Resurface from Route 21 in Jefferson County to Route 32 in Iron County and Route 32 from Route 21 to Bismarck in St. Francis County, the total length of improvement being 41.045 miles.
Job J5P3246 Route 54 CAMDEN County. Pavement improvements from east of Key Largo to east of Route 5, the total length of improvement being 6.31 miles.
Job J5S3306 Route 100 OSAGE County. Slide repair along Route 100 just east of Chamois, the total length of improvement being 0.095 miles.
Job J7S3273 Route Loop 44 LAWRENCE County. Coldmill and resurface from I-44 at Route H to west of I-44 at Route 265 in Mt. Vernon, the total length of improvement being 2.88 miles.
Job J7P3374 Route 13 STONE County. Scour repair from North Connection of BUS 13 to .4 Miles South of Rte OO, the total length of improvement being 1.386 miles.Job J9P3501 Route 67 WAYNE County. Slide repair various locations along Rte. 67 in Wayne County, the total length of improvement being 0.316 miles.

The following five sets of projects were let as one project (for each set):
(1): Job J1I3186 Route Various BUCHANAN County. Bridge rehabilitation various bridge ramps in the Saint Joseph area, the total length of improvement being 0.53 miles.
(2): Job J1P3120 Route 36 BUCHANAN County. Bridge rehabilitation in various locations in St. Joseph, the total length of improvement being 0.229 miles.

(1): Job J4P3081E Route 58 CASS County. Resurface and ADA improvements from Route D to Dean/Avenue/Clint Drive in Belton, the total length of improvement being 4.512 miles.
(2): Job J4P3081H Route Y CASS County. Intersection improvements at MO 58 in Belton, the total length of improvement being 0.142 miles.

(1): Job J5S3268 Route Y, CC, HH PHELPS County. Chip seal Route Y from E To SME, Route CC from Route 63 to SEM, Route HH From E to SME, the total length of improvement being 14.795 miles.
(2): Job J5S3364 Route I- 44 Outer Rd PHELPS County. Resurface and guradrail on Arlington Road from Doolittle to 0.3 miles east of Gasconade River, the total length of improvement being 2.914 miles.

(1): Job J7P3130 Route 83 BENTON, HICKORY County. Resurface from Route 65 to Route 54 on Route 83 and from Route 65 to end of Route on Route MM, the total length of improvement being 32.325 miles.
(2): Job J7S3183 Route A ST CLAIR County. Resurface from Route 52 to Route 13, the total length of improvement being 16.938 miles.

(1): Job J9P3199 Route 60 CARTER County. Resurface from 0.4 miles west of Route y to Freemont, the total length of improvement being 0.581 miles.
(2): Job J9P3200 Route 60 CARTER County. Resurface at County Road 143 to Parsons Drive, the total length of improvement being 6.035 miles.   
« Last Edit: October 03, 2018, 03:06:49 PM by mvak36 »
Logged
Counties: Counties visited
Travel Mapping: Summary

mvak36

  • *
  • Offline Offline

  • Posts: 627
  • 2016 WS champs!!!!

  • Last Login: October 17, 2018, 10:07:50 PM
MODOT Contract Lettings
« Reply #52 on: September 14, 2018, 12:13:56 AM »

October 19, 2018 Letting:

Notable Projects:
Job J1I3017 Route I-35 HARRISON County. Resurfacing from Route N in Eagleville to Route 136 in Bethany, the total length of improvement being 13.944 miles.
Job J2S2176 Route 139 SULLIVAN County. Bridge replacement 0.6 miles south of Newton, the total length of improvement being 0.157 miles.
Job J2P3127 Route 24, 61 MARION County. Coldmill and resurface on eastbound and westbound lanes from 0.3 mile north of Route F to 3.0 miles east of Route 61 near Taylor, the total length of improvement being 29.183 miles.
Job J3I3047 Route 70 LAFAYETTE County. Resurface from Johnson Dr. to Route 13, the total length of improvement being 10.45 miles.
Job J4P3235 Route 92 CLAY County. ADA improvements from Route 33 to Marimack Drive, the total length of improvement being 0.525 miles.
Job J5P3258 Route 87 HOWARD County. Resurface from Glasgow to Route 40, the total length of improvement being 22.093 miles.
Job J5S3256 Route OR 44 LACLEDE County. Resurface North and South in Lebanon, the total length of improvement being 9.68 miles.
Job J5S3286 Route 87 COOPER, MONITEAU County. Microsurface from Route 5 at Boonville to Route O at California, the total length of improvement being 32.727 miles.
Job J6P2325 Route 370 ST CHARLES County. Bridge rehabilitation over Route 94, the total length of improvement being 0.113 miles.
Job J6I3384 Route I-70, I-170, I-55 VARIOUS County. Signing improvements various locations on I-70, I-170, and I-55 in St. Charles County, St. Louis County, St. Louis City, and Jefferson County, the total length of improvement being 20.09 miles.
Job J7P3132 Route 54, LP49 VERNON County. Resurface from Webster Street to I-49 and on Loop 49 through Nevada, the total length of improvement being 5.425 miles.
Job J9P3129 Route 49 IRON County. Bridge replacement over Big Creek, the total length of improvement being 0.404 miles. 

The following six sets of projects were let as one project (for each set):
(1): Job J5S3259 Route C COLE, MONITEAU, MORGAN County. Microsurface and resurface from Route 52 near Versailles to Route 54 in Jefferson City, the total length of improvement being 38.918 miles.
(2): Job J5S3311 Route 50 OR COLE County. Resurface at Route 50, Truman Blvd, Country Club and Big Horn Drive, the total length of improvement being 5.493 miles.

(1): Job J6M0268 Route 44/Maritz ST LOUIS County. Bridge rehabilitation over I-44 in Fenton, the total length of improvement being 0.01 miles.
(2): Job J6M0269 Route I-70 ST LOUIS CITY County. Bridge rehabilitation Adelaide Avenue Bridge over I-70, the total length of improvement being 0.01 miles.

(1): Job J6P3180 Route 141 ST LOUIS County. Coldmill and resurface from I-64 to n/o MO 30, the total length of improvement being 10.955 miles.
(2): Job J6P3200 Route 141 ST LOUIS County. Bridge rehabilitation off-ramp over Woods Mill Road and 141 over Rte 100, Grand Glaize Creek, BNSF RR, and Meramec River, the total length of improvement being 0.491 miles.

(1): Job J7P3139 Route 249 JASPER County. Coldmill and resurface from Route 171 in Carterville to 20th St. in Joplin, the total length of improvement being 7.599 miles.
(2): Job J7S3116 Route LP49 JASPER, NEWTON County. Coldmill and resurface from 10th St. in Webb City to 46th St. in Leawood, the total length of improvement being 6.664 miles.
(3): Job J7S3117 Route LP49 NEWTON County. Coldmill and resurface from south of 46th St. in Leawood to I-49, the total length of improvement being 6.358 miles.

(1): Job J8P3088C Route BUS65 CHRISTIAN County. Intersection improvements South St.,3rd St., & Selmore Rd., the total length of improvement being 0.569 miles.
(2): Job J8P3101 Route BUS 65 CHRISTIAN County. Grading and pavement from Route 65 to just west of Selmore/Route 14 intersection, the total length of improvement being 1.18 miles.

(1): Job J8S3082 Route YY GREENE County. Resurface and add shoulder from 0.2 mile east of Route 65 to Route 125, the total length of improvement being 4.658 miles.
(2): Job J8S3085 Route OR 65 GREENE County. Coldmill and resurface from Division to Sunshine (Eastgate and Ingram Mill), the total length of improvement being 3.286 miles.

EDIT: More projects were added to the letting
Job J5S3049B Route 94 MONTGOMERY County. Resurface from 0.2 mile east of Bluffton Road to Route 19 near McKittrick, the total length of improvement being 9.865 miles.

(1): Job J2I3096 Route I-72 MARION County. Resurface and diamond grinding from 0.2 mile west of Rte. 61 to the Mississippi River in Hannibal, the total length of improvement being 3.299 miles.
(2): Job J2P3128 Route 36 MARION County. Resurface eastbound lanes from 0.4 miles west of BUS. 36 at Monroe City to 0.9 miles east of Route H, the total length of improvement being 12.045 miles.
(3): Job J2P3129 Route 36 MARION County. Resurface and bridge rehabilitation on eastbound lanes from 1.8 miles east of Rte. 24 to Rte. 61 and on westbound lanes from Rte. 61 to 0.5 mile west of Rte. 61 in Hannibal, the total length of improvement being 5 miles.

(1): Job J2P3185 Route 15 MONROE, SHELBY County. Chip seal from 0.2 mile south of Route 36 to Route 154 north junction in Monroe County at Paris, the total length of improvement being 17.89 miles.
(2): Job J2P3190 Route 136 SCHUYLER County. Chip seal from Route 63 to Route A in Downing, the total length of improvement being 11.727 miles.
(3): Job J2P3191 Route 3 RANDOLPH County. Chip seal from Route 24 east junction to Route 129 in Roanoke, the total length of improvement being 9.076 miles.

(1): Job J2S3192 Route E LINCOLN County. Chip seal from Route UU in Silex to Route 61, the total length of improvement being 5.214 miles.
(2): Job J2S3193 Route H LINCOLN County. Chip seal from Route E south junction to Route 47 at Troy, the total length of improvement being 10.988 miles.

(1): Job J9P3196 Route 60 HOWELL County. Resurface from Mountain View to east of Birch Tree, the total length of improvement being 11.474 miles.
(2): Job J9P3202 Route 60 HOWELL County. Resurface from Route NN to County Road 1550, the total length of improvement being 5.338 miles.
(10): Job J3S3141 Route WW JOHNSON County. Seal coat from Route D to Henry CL, the total length of improvement being 7.043 miles.
(11): Job J3S3142 Route E PETTIS County. Seal coat from Route B to Route 52, the total length of improvement being 7.394 miles. 
« Last Edit: October 05, 2018, 05:44:17 PM by mvak36 »
Logged
Counties: Counties visited
Travel Mapping: Summary

mvak36

  • *
  • Offline Offline

  • Posts: 627
  • 2016 WS champs!!!!

  • Last Login: October 17, 2018, 10:07:50 PM
Re: MODOT Contract Lettings
« Reply #53 on: September 27, 2018, 09:56:46 AM »

MODOT recently upgraded their website so I am updating links to the Bid Results and Bid Award Winners lists.

Also, they're starting an Environmental study for the Buck O'Neil Bridge. https://www.modot.org/node/6555
Quote
A potential new river crossing to replace the John Jordan “Buck” O’Neil Memorial Bridge has entered the next phase. The Missouri Department of Transportation (MoDOT) and the City of Kansas City, Missouri are working with the Federal Highway Administration (FHWA) to undertake an environmental study, which is required prior to rehabilitating or replacing the existing bridge. The study is being conducted by Burns & McDonnell in accordance with the National Environmental Policy Act (NEPA).

The environmental study will build on the recently completed planning and environmental linkages (PEL) study to further evaluate options to improve or potentially replace the U.S. 169 bridge over the Missouri River in Kansas City.

As part of the new study the team will evaluate potential impacts to historic structures, including the existing Buck O’Neil Bridge, and other resources in the study area such as public parks, open spaces, cultural assets, and people and businesses in and around the area.  This process is necessary to be in compliance with Section 106 of the National Historic Preservation Act, and as applicable Section 4(f) of the DOT Act.

The study, which is scheduled to conclude in late 2019, will require significant public input in the coming months. Two formal public meeting will be scheduled in 2019. Learn more about the study at www.modot.org/welcome-kansas-city-district

For more information about MoDOT news, projects or events, please visit our website at www.modot.mo.gov/kansascity. For instant updates, follow MoDOT_KC on Twitter, or share posts and comments on our Facebook at www.facebook.com/MoDOT.KansasCity. MoDOT Kansas City maintains more than 7,000 miles of state roadway in nine counties. Sign up online for workzone updates or call 888-ASK-MODOT (275-6636).
« Last Edit: September 27, 2018, 10:12:52 AM by mvak36 »
Logged
Counties: Counties visited
Travel Mapping: Summary

mvak36

  • *
  • Offline Offline

  • Posts: 627
  • 2016 WS champs!!!!

  • Last Login: October 17, 2018, 10:07:50 PM
Re: MODOT Contract Lettings
« Reply #54 on: October 15, 2018, 09:21:16 AM »

November 16, 2018 Letting:

Notable Projects:
Job J1P3188 Route 59 BUCHANAN County. Resurface from Route 752 in St. Joseph to north of Route 45, the total length of improvement being 13.608 miles.
Job J2P2217 Route 65, M LINN, LIVINGSTON County. Alternate Resurfacing from North of CR 228 to Route 36 interchange in Chillicothe and the intersection of Route M and MO 11 to north city limits of Brookfield, the total length of improvement being 1.056 miles.
Job J2P3132 Route 6 ADAIR, SULLIVAN County. Resurface From the Chariton River near Novinger to the east city limits of Green Castle and add rumble strips from the west city limits of Green Castle to Route 129 in Green City in Sullivan County, the total length of improvement being 14.46 miles.
Job J2P3134 Route 79 PIKE County. Resurface and shoulders from 0.9 mile south of Rte. 54 east junction in Louisiana to Lincoln County Line, the total length of improvement being 21.054 miles.
Job J2S3250 Route 81 CLARK, LEWIS County. Resurface from Route 136 in Clark County to Route 16 in Lewis County near Canton, the total length of improvement being 26.273 miles.
Job J3S3087 Route 23 JOHNSON County. Pavement improvements from Route DD to Route 2, the total length of improvement being 16.189 miles.
Job J4I3120 Route I-29 CLAY County. Coldmill and resurface from Vivion Road to I-29/35 split, the total length of improvement being 1.996 miles.
Job J4Q3234 Route Various CLAY, PLATTE County. ITS improvements in various locations in Clay and Platte counties, the total length of improvement being 56.8 miles.
Job J5P3214 Route Various CRAWFORD, IRON County. Microsurface and ADA improvements Rte. 19 & Rte. ZZ in Crawford Co. & Rte. 49 beginning in Crawford Co. and ending in Iron Co., the total length of improvement being 46.86 miles.
Job J5S3271 Route Various CAMDEN, MILLER County. Coldmill, resurface, microsurface and shoulder widening on various locations on Route KK, MM, 242 and Bus. Route 54 in Camden and Miller Counties, the total length of improvement being 7.949 miles.
Job J5P3197 Route 17 MILLER, PULASKI County. Microsurface from Route 42 to I-44 Spur and then from I-44 to Route 32, the total length of improvement being 49.122 miles.
Job J5P3186 Route 63, 133 OSAGE County. Intersection improvements just north of Westpahlia, the total length of improvement being 0.392 miles.
Job J6I3251 Route I-70 ST LOUIS County. Bridge painting over McKelvey Road and Route 141, the total length of improvement being 1.446 miles.
Job J7I3084 Route I-44 JASPER, NEWTON County. Coldmill and resurface from 0.4 miles east of Loop 49 in Joplin to 1.5 miles east of Route 37 in Sarcoxie, the total length of improvement being 37.43 miles.
Job J7P3355 Route 249 JASPER County. Job Order Contract for slide repairs from Rte. 171 in Carterville to Rte. VV (Zora Street) near Joplin, the total length of improvement being 2.314 miles.
Job J9S3294 Route 49 WAYNE County. Resurface from Rte. 34 to Rte. 67, the total length of improvement being 22.056 miles.

The following six sets of projects were let as one project (for each set):
(1): Job J1P3024 Route 5 CHARITON County. Resurface and shoulder widening from Route M to Route O south of Brookfield city limits, the total length of improvement being 19.506 miles.
(2): Job J1S3170B Route 129 CHARITON County. Resurface from Route W to Route PP near Salisbury, the total length of improvement being 7.24 miles.

(1): Job J4I3122 Route I-435 PLATTE County. Coldmill and resurface from I-29 South to west of Cookingham Drive, the total length of improvement being 5.19 miles.
(2): Job J4S3277 Route D PLATTE County. Coldmill and resurface from I-29 to Cookingham Dr, the total length of improvement being 1.413 miles. 

(1): Job J5P3114 Route 63 MARIES, PHELPS County. Coldmill, and resurface from north of Vichy to Rolla, the total length of improvement being 12.49 miles.
(2): Job J5P3233 Route 63 MARIES, OSAGE County. Coldmill and resurface from Route 50 to 4 miles south of Vienna, the total length of improvement being 26.74 miles.

(1): Job J5P3235 Route 63 BOONE County. Coldmill and resurface from Route F/22 Interchange to Route 763, the total length of improvement being 29.606 miles.
(2): Job J5S3159B Route 763 BOONE County. Coldmill and resurface from Bus Loop 70 to Stadium Blvd in Columbia, the total length of improvement being 2.024 miles.

(1): Job J7S3133 Route 160, 13 CHRISTIAN, STONE County. Resurface from 0.4 miles north of Finley Creek to Reeds Spring Junction and on Rte. 13 from Reeds Spring Junction to Table Rock Lake, the total length of improvement being 28.798 miles.
(2): Job J8P3051D Route 160 CHRISTIAN County. Resurface from South Street in Nixa to 0.4 miles north of Finley Creek., the total length of improvement being 3.191 miles.

(1): Job J9S3240 Route H SCOTT County. Resurface from Route 77 to Route U, the total length of improvement being 5.77 miles.
(2): Job J9S3406 Route E SCOTT County. Resurface from Route 77 to Commerce, the total length of improvement being 7.913 miles.
(3): Job J9S3438 Route 61 SCOTT County. Resurface from south of Route K to north of Route 77, the total length of improvement being 12.456 miles.