NCDOT has released its Draft 2020-2029 STIP document. I quickly perused it for updated construction schedules for Interstate projects. Some of the highlights:
I-73/I-74
R-3421 I-73/74 Rockingham Bypass. Construction from late 2019 to 2023, partly financed by Build NC Bonds to be paid back by 2034, US 1 interchange improvements (I-5979) at US 74 Construction 2022
I-6055 I-74 Upgrade in Richmond and Scotland County, ROW 2025/26 Construction in 2029
I-785
R-5889 Upgrade US 29 to Interstate Standards from Hicone Road to US 29 Bypass in Reidsville, Construction 2027
I-87
R-5869 Upgrade US 17 intersections to interchanges in Perquimans County, Construction 2028
I-6041 and 6046 US 64 Pavement Rehabilitation I-95 to NC 33 in Edgecombe and Nash County, Construction 2020
I-6042 US 64 Pavement Rehabilitation NC 33 to Martin County Line, Construction 2022
U-6149 Upgrade US 64 to Interstate Standards from NC 58 to Thomas Rd overpass in Nash and Edgecombe Counties Construction After 2029
I-587
I-6032 US 264 Pavement Rehabilitation Greene County Construction 2019
I-6035 US 264 Pavement Rehabilitation Pitt County Construction 2019
I-42
I-6002 US 70 Pavement Rehabilitation in Craven and Jones County, Construction 2019
I-6004 US 70 Pavement Rehabilitation in Johnston County from Buffaloe Rd to Wayne County Line, Construction 2019
R-2553 US 70 Upgrade end of Goldsboro Bypass to New Bern Freeway Construction 2025-2028
I-795
U-3125 Extension Goldsboro to I-40 Country Club Rd (SR 1135)to S. Landfill Rd (SR 1129) Construction 2027 Goldsboro Area ROW 2028
The complete document is at:
https://www.ncdot.gov/initiatives-policies/Transportation/stip/development/Pages/draft-stip-highlights.aspx