Ramps from both directions of I-135 converge within a half mile of Exit 1B for MacArthur Road.
10/04/21

The interchange sequence sign posted three miles from Exit 5 originally displayed K-2 alongside K-42 for Southwest Boulevard.
10/31/16

Underway from November 2015 to Summer 2019, the Red Project converted the exchange at Exit 7 into a cloverstack with two flyovers linking I-235 and U.S. 54/400 (Kellogg Avenue).
10/04/21

The future Blue Project will replace the remaining two loop ramps at U.S. 54/400 (Kellogg Avenue) with flyovers.
10/04/21

Flyovers connecting I-235 north with 13th Street N at Exit 9 were constructed from late 2012 to November 2014.
11/01/16

The directional T interchange with K-96 overlays part of the diamond interchange with adjacent Meridian Avenue.
11/01/16