Part of the Wichita North Junction Gold Project Sub-Phase (Phase 2A), construction from April 2021 to December 2023 builds a two lane flyover from I-135/K-96 north to I-235 and replaces the ramp from I-135 south to I-235.
10/05/21

The Wichita North Junction Green Project through November 2021 rebuilt the southbound roadway for I-235/K-96 and reconfigured the folded diamond interchange (Exit 15) at Broadway Avenue with longer ramps.
10/05/21

The Green Project phase of the Wichita North Junction Project replaced bridges across the LIttle Arkansas River, Arkansas Avenue and Broadway Avenue. Costing $65 million, work ran from March 2019 to November 2021.
10/31/16

The Seneca Avenue bridge spanning I-235/K-96 ahead of Exit 13 was removed during the Green Project.
10/31/16